File #: 2023-3259    Version: 1 Name:
Type: Consent Status: Passed
File created: 10/5/2023 In control: OPERATIONS COMMITTEE
On agenda: 10/25/2023 Final action: 10/25/2023
Title: REHABILITATION OF WESTERN REGIONAL SEWERS, PROJECT NO. 3-64
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. GSWC Agreement
Related files: 2022-2560

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

REHABILITATION OF WESTERN REGIONAL SEWERS, PROJECT NO. 3-64

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Approve an agreement with the Golden State Water Company for the relocation of their water line in coordination with the Rehabilitation of Western Regional Sewers, Project No. 3-64;

 

B.       Approve an additional deposit in the amount of $280,198, for a total deposit amount of $282,698; and

 

C.       Approve a contingency of $28,270 (10%).

body

 

BACKGROUND

 

The Orange County Sanitation District (OC San) has a project in the city of Cypress that will replace the existing 18-inch sewer with a new larger 24-inch sewer pipeline in the same alignment.  This project will also replace the manholes to accommodate the new larger pipe.  One of the manholes to be replaced is located near a Golden State Water Company (GSWC) water pipeline.  As part of the project, the area around the manhole will be excavated and utilities within that area will be relocated or protected in place.

 

RELEVANT STANDARDS

 

                     Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities

 

PROBLEM

 

The GSWC water pipeline conflicts with OC San’s proposed construction.  This pipeline needs to be relocated and GSWC needs to perform the work to ensure it complies with drinking water standards.

 

 

 

 

PROPOSED SOLUTION

 

Approve an agreement with GSWC for the relocation of GSWC water pipeline.  GSWC will move the pipeline out of the conflict zone within the OC San construction work area.

 

TIMING CONCERNS

 

If the approval of the agreement is delayed, it could delay the advertisement of the project, which is currently planned for Spring 2024.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

The construction costs will increase and the schedule may be extended.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

An Environmental Impact Report (State Clearinghouse Number 2015111077) was prepared for “Rehabilitation of Western Regional Sewers Project No. 3-64”, certified by the Board of Directors, and a Notice of Determination was filed on March 23, 2017.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update, Fiscal Year 2023-2024, Appendix A, Page 7, Rehabilitation of Western Regional Sewers, Project No. 3-64) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Agreement

 

HK: jw