File #: 2025-4089    Version: 1 Name:
Type: Consent Status: Passed
File created: 1/27/2025 In control: OPERATIONS COMMITTEE
On agenda: 3/5/2025 Final action: 3/5/2025
Title: COLLECTION SYSTEM SPARE PUMP PROCUREMENT FOR THE WESTSIDE AND COLLEGE PUMP STATIONS
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report
Related files: 2021-1488

FROM:                     Robert Thompson, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance 

 

SUBJECT:

 

title

COLLECTION SYSTEM SPARE PUMP PROCUREMENT FOR THE WESTSIDE AND COLLEGE PUMP STATIONS

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.                        Approve a Sole Source Purchase Order to Flo-Systems, Inc. for the purchase of two spare rotating pump assemblies: one rotating assembly for the Westside Pump Station and one rotating assembly for the College Pump Station, for a total amount not to exceed $225,349, including applicable sales tax and freight; and

 

B.       Approve a contingency of $22,535 (10%).

body

 

BACKGROUND

 

The Orange County Sanitation District (OC San) operates 15 pump stations within its regional collection system.  The pump stations lift wastewater from low points where the gravity flow system cannot be used to transport wastewater to the treatment plants.  The pumps in these stations require routine removal and restoration activities to maintain design capacity output due to normal wear and tear.  These pump stations are critical to the collection system operation and may result in a backup or sewer spill in the event of losing pumping capacity.

 

RELEVANT STANDARDS

 

                     Achieve less than 2.1 sewer spills per 100 miles

                     Commitment to safety & reducing risk in all operations

                     Protect OC San assets

 

PROBLEM

 

The main lift pumps at College and Westside Pump Stations require removal for overhauls.  However, without spare replacements on hand, this process leads to a temporary loss of pumping capacity.  Additionally, the extended lead times in modern supply chains for required overhaul services reduce system redundancy, increasing the risk of service disruptions.

 

PROPOSED SOLUTION

 

Approve the purchase of spare rotating pump assemblies from Flo-Systems, Inc. for the Westside and College pump stations to maintain asset availability and minimize operational downtime.

 

TIMING CONCERNS

 

The spare pump assemblies identified for purchase have a lead time of up to 25 weeks, or longer, depending on availability.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Loss of pumping capacity at the pump stations due to long lead times for spare pumps increases the risk of a sewer spill.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

February 2021 - Approved Hidrostal, LLC to the Original Equipment Manufacturer (OEM) Sole Source List for pumps and replacement parts.

 

ADDITIONAL INFORMATION

 

Flo-Systems, Inc. is the sole approved representative authorized by Hidrostal, LLC to sell the subject pump assemblies.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance. This item has been budgeted (Budget FY 2024-25 and 2025-26, Section 8, Page 89, Collection Facilities Operations and Maintenance) and the budget is sufficient for the recommended  action.

 