Legislation Details

File #: 2026-5203    Version: 1 Name:
Type: Non-Consent Status: Final
File created: 11/13/2026 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2026 Final action:
Title: DEEP WELL INJECTION FACILITY, PROJECT NO. J-143
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Draft Progressive Design-Build Contract, 3. Presentation

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

DEEP WELL INJECTION FACILITY, PROJECT NO. J-143

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Approve a Progressive Design-Build Contract with Filanc to provide Phase 1 engineering and preconstruction services, for the Deep Well Injection Facility, Project No. J-143, for a total amount not to exceed $13,477,557; and

 

B.       Approve a contingency of $1,347,756 (10%).

body

 

BACKGROUND

 

The Orange County Sanitation District (OC San) treats wastewater at Plant Nos. 1 and 2 and generates biosolids that are transported off site for management and beneficial use.   OC San has studied deep well injection as a potential long-term option for managing these solids.

 

Deep well injection would place processed solids into suitable deep underground formations.  Initial surface facilities would serve Plant No. 1. Future facilities at Plant No. 1 could consist of a receiving station for Plant No. 2 biosolids, an interplant sludge line, or an alternate solution at Plant No. 2.

 

OC San selected Progressive Design-Build (PDB) delivery to develop design, cost, and risk information in stages before deciding whether to proceed with construction.

 

RELEVANT STANDARDS

 

•                     Ensure the public's money is wisely spent

•                     Comply with environmental permit requirements

•                     Sound engineering and accounting practices, complying with local, state, and federal laws

•                     Maintain a culture of improving efficiency to reduce the cost to provide the current service level or standard

 

 

 

 

PROBLEM

 

OC San currently relies on third-party contracts for long-distance hauling and off-site management of biosolids.  This creates ongoing transportation costs and exposes OC San to changes in available off-site management options.  OC San is also impacted by the changing biosolids market conditions.

 

OC San has determined that deep well injection is feasible using historical well drilling information, but needs to confirm the local geologic conditions and injection performance of a full-scale system by constructing a test well.

 

PROPOSED SOLUTION

 

Approve the Phase 1 PDB Contract to advance the engineering and preconstruction services needed to evaluate deep well injection at Plant No. 1.  The design-builder will design the initial test well, coordinate subsurface investigations and permitting, and develop the cost and schedule information needed for future decisions, and advance preliminary design for the potential full-scale facilities.

 

Under Phase 1 PDB, OC San will negotiate a GMP for permitting, construction, and testing of the initial test well, and will go to the Board to request a revised upper limit.  Results from the test well will confirm subsurface conditions and determine the feasibility and size of the full-scale deep well injection facility.  A second GMP will include Phase 2 design and full-scale facility construction.  A third GMP will include extended commissioning.

 

TIMING CONCERNS

 

Delaying the Phase 1 award would postpone subsurface investigations, permitting support, and development of the test well GMP.  This would defer decisions on the project's feasibility and costs.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Without this contract, OC San would not advance evaluation of deep well injection as a potential long-term biosolids management option and would continue relying on its existing off-site management contracts.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

Design-Builder Selection:

 

OC San held a Market Sounding and Industry Forum on December 15, 2025, to assess the industry interest in the Project and gather feedback from potential proposers before the actual Request for Proposals (RFP) was published.  The event was well attended with over 39 participants from multiple professional firms.  OC San also met individually with three interested firms on February 24 and 25, 2026, to discuss project requirements and risks.

 

On June 16, 2026, OC San issued a Request for Proposals (RFP) through OpenGov and advertised it in the Orange County Register.  A mandatory pre-proposal meeting and site visit were held on June 25, 2026, followed by optional proprietary meetings on July 9, 2026.

 

The RFP established the following technical and price evaluation criteria:

 

Description

Points

TECHNICAL PROPOSAL EVALUATION CRITERIA

Proposer Profile and Minimum Requirements

Responsive / Non-Responsive

Project Understanding and Key Issues

30

Project Team and Key Personnel

15

Project Experience and References

10

Project Delivery and Management Approach

15

Cost Development and Procurement Approach

10

Technical Proposal Maximum Score

80

PRICE PROPOSAL EVALUATION CRITERIA

Phase 1 Engineering and Preconstruction Services Cost

10

Phase 2 Design-Builder’s Fee

10

Price Proposal Maximum Score

20

TOTAL PROPOSAL MAXIMUM SCORE

100

 

 

Two proposals were received on August 11, 2026, from Filanc and Terralog Technologies Inc., (Terralog).  Filanc’s proposal was found responsive.  Terralog's alternative services proposal was found nonresponsive because it did not meet the RFP's mandatory Phase 1 PDB scope and contractual requirements.  Specifically, the proposal focused primarily on the test well and formation-testing program rather than the full Phase 1 PDB scope, deferred significant design and construction activities to Phase 2, did not clearly commit to the required open-book cost and GMP process, and proposed changes to the Design-Builder’s performance obligations and allocation of costs, responsibilities, and risks.  Therefore, only Filanc was evaluated and scored.

 

 

 

 

 

 

 

 

 

 

 

 

OC San conducted a one-step, best-value procurement under Public Contract Code section 22185 and its Purchasing Ordinance.  Filanc's technical proposal was scored on August 25, 2026, and an interview was conducted on September 3, 2026.  The technical scores are summarized below:

 

Evaluation Criterion

Maximum Points

Initial Technical Score

Final Technical Score

Project Understanding and Key Issues

30

23

26

Project Team and Key Personnel

15

12

13

Project Experience and References

10

8

8

Project Delivery and Management Approach

15

11

12

Cost Development and Procurement Approach

10

6

6

TECHNICAL PROPOSAL TOTAL

80

60

65

 

Following completion of the technical evaluation, Contracts Administration opened the responsive price proposal and applied the scoring method specified in the RFP.  The final technical, price, and total scores were as follows:

 

Proposer

Final Technical Score (80)

Phase 1 Price (10)

Phase 2 Fee (10)

Total (100)

Filanc

65

10

10

85

 

The Evaluation Committee determined that Filanc offered the best overall value based on the qualifications of its integrated team, relevant wastewater and deep well injection experience, project-delivery approach, safety and financial qualifications, and open-book cost-development strategy.  Filanc's team includes Brown and Caldwell and Advantek, with capabilities pertinent to subsurface conditions, deep well engineering, permitting, surface integration, and operations.  Because Filanc was the only responsive proposer, it received the maximum 20 price points under the RFP's established scoring methodology.  Since no other responsive price proposals were available for comparison, OC San separately evaluated the reasonableness of Filanc's proposed costs through detailed cost reviews and negotiations.

 

On September 3, 2026, the Evaluation Committee recommended negotiations with Filanc.

 

Negotiations:

 

Negotiations with Filanc began on September 10, 2026, and focused on the Phase 1 scope, schedule, cost, and contract terms.

 

Staff refined the Phase 1 design deliverables and made the 90-percent design package an optional service requiring separate OC San authorization.  The scope focuses on engineering, permitting support, and development of future GMP proposals.

 

The contract anticipates a separate GMP for initial test well construction and testing, followed by future GMPs for full facility construction and extended commissioning.  Each future GMP will require separate negotiation and Board approval to increase to the upper limit.

 

Negotiations also clarified that the injection and monitoring wells would be designed and permitted to accommodate potential solids loading from both treatment plants, while the initial surface facilities would serve Plant No. 1 only.  Future Plant No. 2 surface facilities would be addressed separately.

 

Staff reviewed proposed labor hours and rates, subcontractor markups, specialized services, and allowances to better align pricing with the revised Phase 1 scope.  The proposed time-and-materials contract has a not-to-exceed amount, with separate authorization required for optional work.

 

The negotiated Phase 1 price is summarized as follows:

 

 

Original Amount

Final Negotiated Amount

Phase 1 Services

$13,612,650

$10,652,201

Optional item

Negotiated allowance

Task 3.5 - 90% Design (includes 3.7-3.9)

$2,345,757

Subtask 6.2 - Sludge Batch Testing

$173,109

Subtask 6.3 - Seismic / Reservoir Software

$306,490

TOTAL OPTIONAL ALLOWANCES

$2,825,356

TOTAL PHASE 1 INCLUDING OPTIONS

$13,477,557

 

Based on the results of these negotiations, staff determined that the final negotiated fee is fair and reasonable for this project and recommends awarding the PDB Contract to Filanc.

 

CEQA

 

CEQA environmental impact report (EIR) will be started during Phase 1 design and finalized after the initial test well is drilled and deep well injection capacity and facility size is determined.

 

FINANCIAL CONSIDERATIONS

 

This request is subject to the authority levels of OC San's Purchasing Ordinance.  This item has been budgeted (Budget FY 2026-27 and FY 2027-28, Section 8, Page 45, Deep Well Injection Facility, Project No. J-143).  The design-builders initial budgetary estimate is greater than the current project budget.  OC San will be requesting additional project budget after the well capacity and facility size is determined.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

•                     Draft Progressive Design-Build Contract

•                     Presentation

 

MS:lb