FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

ACTIVATED SLUDGE CLARIFIER REPAIRS AT PLANT NO. 2, PROJECT NO. FR2-0018R

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Receive and file Bid Tabulation and Recommendation for Activated Sludge Clarifier Repairs at Plant No. 2, Project No. FR2-0018R;

 

B.       Award a Construction Contract to Garney Pacific, Inc. for Activated Sludge Clarifier Repairs at Plant No. 2, Project No. FR2-0018R for an amount of $5,091,686; and

 

C.       Approve a contingency of $509,169 (10%).

body

 

BACKGROUND

 

The Activated Sludge facility at Orange County Sanitation District (OC San) Plant No. 2 uses chain and flight mechanisms to collect sludge settling along the length of the rectangular clarifiers and to deliver the sludge to hoppers located at the upstream end.  The collectors, which include 2,900 feet of plastic chains and 160 flights per clarifier, are subject to degradation and wear.  The collector mechanisms were replaced in six of the clarifiers in 2020; the collectors in the remaining six clarifiers have been in service since 1996.

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

                     Maintain a proactive asset management program

 

PROBLEM

 

The collectors in six of the clarifiers are at the end of their useful life, resulting in a number of recent total failures that required expensive repairs during which the clarifiers were unavailable for service for many weeks.

 

 

PROPOSED SOLUTION

 

Award a Construction Contract for Activated Sludge Clarifier Repairs at Plant No. 2, Project No. FR2-0018R.  This project will replace the sludge collection mechanisms in the six remaining clarifiers.

 

TIMING CONCERNS

 

The collectors will continue to require frequent maintenance.  The clarifiers must be reliable so that the Activated Sludge facility at Plant No. 2 will have sufficient capacity to handle peak wet weather flows.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

The reliable operation of the clarifiers will remain compromised.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

February 2022 - Board received and filed Bid Tabulation and Recommendation for Activated Sludge Clarifier Repairs at Plant No. 2, Project No. FR2-0018; received and filed award protests; received and filed determination letter recommending rejection of all bids and re-advertising the project; and rejected all bids and directed staff to re-advertise this project for bids.

 

ADDITIONAL INFORMATION

 

This project was advertised for bids in late 2021, but due to erroneous instructions in the Invitation for Bids, OC San was not able to award a contract.

 

OC San then re-advertised Project No. FR2-0018R for bids on March 10, 2022.  The bid package was modified slightly to clarify commissioning requirements and to increase the contract duration by 40 days.

 

Eight sealed bids were received on April 26, 2022.  A summary of the bid opening follows:

 

Engineer’s Estimate

$ 4,836,000

Bidder

Amount of Bid

Garney Pacific, Inc.

$ 5,091,686

J.R. Filanc Construction Co., Inc.

$ 5,119,910

W.M. Lyles Co.

$ 5,149,000

Abhe & Svoboda, Inc.

$ 5,233,609

Mehta Mechanical Company, Inc. dba MMC Inc.

$ 5,537,881

Houalla Enterprises, Ltd. dba Metro Builders & Engineers Group, Ltd.

$ 5,885,525

Myers & Sons Construction, LLC

$ 5,916,000

Shimmick Construction Company, Inc.

$ 6,147,083

 

The bids were evaluated in accordance with the OC San’s policies and procedures and the apparent low bidder, Garney Pacific, Inc., was found to be responsive and responsible.  A notice was sent to all bidders on June 6, 2022 informing them of the intent of OC San staff to recommend award of the Construction Contract to Garney Pacific, Inc.  Staff recommends awarding a Construction Contract to the lowest responsive and responsible bidder, Garney Pacific, Inc., for a total amount not to exceed $5,091,686.

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301.  A Notice of Exemption has been filed with the OC Clerk-Recorder.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This recommendation will be funded under the Repairs and Maintenance line item for Division 880, Plant No. 2 Maintenance (Adopted Budget, Fiscal Year 2022-2023 and 2023-2024, Section 6, Page 96) and the available funding is sufficient for this action.

 

ATTACHMENT