File #: 2021-1532    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 3/9/2021 In control: OPERATIONS COMMITTEE
On agenda: 7/7/2021 Final action: 7/7/2021
Title: SUNFLOWER AND RED HILL INTERCEPTOR REPAIRS, PROJECT NO. 7-66
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. 7-66 PCSA Package - GHD Inc, 3. Presentation - 7-66_PCSA
Related files: 2019-605, 2021-1758

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

SUNFLOWER AND RED HILL INTERCEPTOR REPAIRS, PROJECT NO. 7-66

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Approve a Professional Construction Services Agreement with GHD, Inc. to provide construction support services for Sunflower and Red Hill Interceptor Repairs, Project No. 7-66, for an amount not to exceed $166,000; and

 

B.       Approve a contingency of $16,600 (10%).

 

body

BACKGROUND

 

GHD, Inc. was selected as part of a competitive, qualifications-based solicitation process to design the Sunflower and Red Hill Interceptor Repairs, Project No. 7-66.  At the time of the solicitation, the Orange County Sanitation District (OC San) documented its intent to award a subsequent agreement to the design consultant for continuation of engineering services during construction.

 

This project will award a construction contract for the Sunflower and Red Hill Interceptor Repairs, Project No. 7-66.  The work will repair PVC liner failures within a 6,000-foot section of the Sunflower and Red Hill Interceptors.  This work will reduce the risk of a sewage spill, pipeline failure, and extend the useful life of the assets.

 

RELEVANT STANDARDS

 

                     Comply with California Government Code Section 4526 to engage the best qualified firm “on the basis of demonstrated competence and qualifications” and “negotiate fair and reasonable fees”

                     Ensure the public’s money is wisely spent

 

PROBLEM

 

This project requires the design consultant to provide as-needed services during construction including submittal review, responding to the Contractor’s requests for information, reviewing construction change orders, participating in meetings, attending site visits, and preparing record drawings.

 

PROPOSED SOLUTION

 

Award a Professional Construction Support Services Agreement with the design consultant, GHD, Inc., to provide engineering support services during construction.

 

TIMING CONCERNS

 

Engineering support services will be required at the start of construction.  Construction is anticipated to start in August 2021.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

The engineering support services needed to facilitate and review construction activities would not be available by the Engineer of Record, which may negatively impact the contract execution.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

September 2019 - Approved a Professional Design Services Agreement with GHD, Inc., to provide engineering services for Sunflower and Red Hill Interceptor Repairs, Project No. 7-66, for an amount not to exceed $308,712, and approved a contingency of $30,871 (10%).

 

ADDITIONAL INFORMATION

 

GHD, Inc. has successfully furnished engineering design services for Sunflower and Red Hill Interceptor Repairs, Project No. 7-66, and their support services during construction will provide continuity through the completion of the project.

 

Staff negotiated with GHD, Inc. for these construction support services in accordance with OC San’s adopted policies and procedures.  The proposed fees are based on estimated quantities provided by OC San for requests for information, submittal reviews, meetings, site visits, change order reviews, and design revisions, as well as the level of effort for preparing record drawings.  Staff has determined the negotiated fee to be fair and reasonable for these services.

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301.  A Notice of Exemption was filed with the OC Clerk-Recorder after OC San’s Board of Directors approved the Professional Services Design Agreement.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update, Fiscal Year 2021-2022, Appendix A, Page A-7, Sunflower & Red Hill Interceptor Repairs, Project No. 7-66) and the budget is sufficient for the recommended action.

 

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Professional Construction Services Agreement

                     Presentation

 