File #: 2023-2792    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 2/2/2023 In control: OPERATIONS COMMITTEE
On agenda: 2/22/2023 Final action: 2/22/2023
Title: LONG LEAD TIME AUDIO VISUAL EQUIPMENT PURCHASE FOR HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A
Sponsors: Kathy Millea
Attachments: 1. Agenda Report
Related files: 2023-2699, 2023-2953

FROM:                     Robert Thompson, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:   

 

title

LONG LEAD TIME AUDIO VISUAL EQUIPMENT PURCHASE FOR HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

Approve a Purchase Order to AVI-SPL LLC for the purchase of Audio Visual Equipment, Specification No. E-2022-1374BD, for a total amount not to exceed $911,309 plus applicable sales tax.

body

 

BACKGROUND

 

Orange County Sanitation District (OC San) is constructing a new headquarters building under Project No. P1-128A.  The new headquarters will require audio-visual equipment to function properly.  The construction contract for the project does not include the audio-visual integrator services, which has been planned to be procured through a separate public works contract and includes the purchase and installation of this necessary audio-visual equipment.

 

RELEVANT STANDARDS

 

                     Ensure the public’s money is wisely spent

                     Maintain a culture of improving efficiency to reduce the cost to provide the current service level or standard

 

PROBLEM

 

A number of items with long lead times due to ongoing supply chain issues were identified during the development of the audio-visual integrator contract.  If these items are purchased through the audio-visual integrator contract, which is still in development, they could delay the completion of the new headquarters.

 

PROPOSED SOLUTION

 

Approve a Purchase Order to procure the equipment with long lead times ahead of the audio-visual integrator contract so the parts will be available in time for installation.

 

TIMING CONCERNS

 

All audio-visual equipment is required by October 2023 to maintain the current headquarters construction schedule.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

The completion of the new headquarters will be delayed if all audio-visual equipment is not available in time for installation under the current construction schedule.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

A Notice Inviting Bids was issued on November 1, 2022, via PlanetBids.  Bids were due on December 6, 2022.  OC San received three (3) total bids valid for 180 calendar days from the bid opening date.  Of the three bids received, one was considered non-responsive as the bidder skipped some bid items and provided pricing for unapproved alternative equipment.  One bid was withdrawn by the bidder as they skipped some bid items and could not hold their pricing shortly after the bid date.

 

The estimated bill of material was $1,000,000.  The following is a list of the firms who submitted a bid:

 

Company Name

Bid

Determination

Adorama Inc.

$ 85,491.73

Non-Responsive

Ford Audio Video LLC

$446,685.00

Withdrawn

AVI-SPL LLC

$911,308.70

Responsive

 

The bids were evaluated in accordance with OC San policies and procedures.  The first two bidders were deemed to have not included multiple bid items as required.  For those bid items that were submitted by all bidders, AVI-SPL LLC’s bid was competitive.  Based on these results, staff recommends approving a Purchase Order to AVI-SPL LLC.  A notice was sent to all the bidders on December 15, 2022, informing them of the intent of OC San to recommend approval of a purchase order to AVI-SPL LLC.

 

CEQA

 

N/A

 

 

 

 

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Adopted Budget, Fiscal Years 2022-2023 and 2023-2024, Section 8, Page 55, Headquarters Complex, Project No. P1-128) and the budget is sufficient for the recommended action. 

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

N/A

 

AB: jw