File #: 2026-4851    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 3/17/2026 In control: STEERING COMMITTEE
On agenda: 3/25/2026 Final action: 3/25/2026
Title: PLANT NO. 1 ADDED FACILITIES AGREEMENT RENEWAL WITH SOUTHERN CALIFORNIA EDISON COMPANY
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report, 2. Added Facilities Agreement
Related files: 2026-4813

FROM:                     Robert Thompson, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance 

 

SUBJECT:

 

title

PLANT NO. 1 ADDED FACILITIES AGREEMENT RENEWAL WITH SOUTHERN CALIFORNIA EDISON COMPANY

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

Approve the Added Facilities Agreement with Southern California Edison Company and Orange County Sanitation District, for the Orcosan Substation at Plant No. 1, AF00801-001, ensuring perpetual replacement cost coverage.

body

 

BACKGROUND

 

Both Orange County Sanitation District’s (OC San) Plant No. 1 and Plant No. 2 have dedicated electrical substations, designated as Orcosan and Orcogen respectively, which connect them to the Southern California Edison Company (SCE) power grid. Substations contain equipment that transforms the high voltage (66 kV) from SCE to the lower voltage (12.5 kV) required by the treatment plants. While OC San pays for the substation equipment, ownership remains with SCE.

 

Under a 20-year Added Facilities Agreement (AFA) signed in April 2006, OC San pays a monthly fee to SCE for the Plant No. 1 Orcosan substation equipment, including replacements during the AFA term. Currently, this fee is $16,593.80.

 

RELEVANT STANDARDS

 

                     Ensure the public’s money is wisely spent

                     Maintain a culture of improving efficiency to reduce the cost to provide the current service level of standard

 

PROBLEM

 

The existing AFA for Plant No. 1 Orcosan substation will expire on April 20, 2026. SCE has offered three renewal options:

 

1)                     Terminate the AFA service: SCE would remove the Added Facilities equipment and revert to providing standard electrical service.

2)                     Extend AFA service without replacement: AFA equipment would remain in place but would not be replaced if needed. The monthly fee would decrease by $1,005, to approximately $15,588, but OC San would be responsible for all equipment replacements as they occur.

3)                     Extend AFA service with replacement coverage in perpetuity: A new AFA with equipment replacement in perpetuity would increase the monthly fee by about $3,000, and OC San would pay a one-time “Make-Whole Payment” of $1,633,223 to account for the difference between the amount SCE received under the 20-year AFA and the actual replacement costs.

 

PROPOSED SOLUTION

 

OC San staff reviewed the three options and recommends Option (3) to provide uninterrupted electrical service to Plant No. 1, along with certainty about future costs for equipment replacements as they are needed.

 

TIMING CONCERNS

 

The current 20-year AFA expires April 2026 and will not automatically renew.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If a new AFA is not enacted, electrical service to Plant No. 1 would revert to SCE’s standard low voltage service which will  require costly modifications to the electrical systems. This would also decrease the stability and reliability of our electrical system, and increase our electrical costs, because the lower cost, and higher voltage service would no longer be available, and could potentially lead to a service interruption during the transition.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

March 2006 - Approved a Sole Source Agreement with Southern California Edison for engineering services, fees, materials, and labor for 66 kV Substation at Plant No. 1, Job No. P1-97, for an amount not to exceed $6,052,000; approved a monthly charge of $15,732 for maintenance and equipment replacement costs; and increased the project budget in the amount of $4,302,947 for a total amount of $9,475,538.

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

Not having an AFA in place could increase electricity costs and would expose OC San to equipment price increases and budgeting uncertainty for necessary equipment replacements. This item is budgeted in the Operations & Maintenance Budget - Division 830 Repairs & Maintenance, Budget Update FY 2025-26 page 33.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Added Facilities Agreement

 

RM:jb:ls