File #: 2020-1272    Version: 1 Name:
Type: Consent Status: Withdrawn
File created: 9/25/2020 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2020 Final action: 12/2/2020
Title: PLANT WATER PIPELINE REPLACEMENT IN KINNISON, LINDSTROM, AND SCOTT TUNNELS AT PLANT NO. 2, PROJECT NO. FE18-14
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. FE18-14 Draft Contract Agreement
Related files: 2020-1373

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

PLANT WATER PIPELINE REPLACEMENT IN KINNISON, LINDSTROM, AND SCOTT TUNNELS AT PLANT NO. 2, PROJECT NO. FE18-14

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Receive and file Bid Tabulation and Recommendation for Plant Water Pipeline Replacement in Kinnison, Lindstrom, and Scott Tunnels at Plant No. 2, Project No. FE18-14;

 

B.       Award a Construction Contract to MMC Inc. for Plant Water Pipeline Replacement in Kinnison, Lindstrom, and Scott Tunnels at Plant No. 2, Project No. FE18-14, for a total amount not to exceed $1,134,000; and

 

C.       Approve a contingency of $170,100 (15%).

body

 

BACKGROUND

 

Plant water is screened and chlorinated secondary effluent used wherever higher-quality potable water is not necessary, such as for washdown or cooling.  Plant water is somewhat corrosive leading to corrosion in metallic pipes.  Plant water pipelines, along with many other utilities, are often located in tunnels throughout the plants so that they can be readily accessed and maintained.

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award Construction Contract to lowest responsive, responsible bidder

                     Maintain a proactive asset management program

 

PROBLEM

 

Many of the plant water pipelines in the Kinnison, Lindstrom, and Scott Tunnels have been in place for decades and consist of pipes and appurtenances made from steel and ductile iron.  The plant water system in these tunnels has a long history of leaks requiring emergency repair work.

 

 

PROPOSED SOLUTION

 

Award a Construction Contract for Plant Water Pipeline Replacement in Kinnison, Lindstrom, and Scott Tunnels at Plant No. 2, Project No. FE18-14.  This project will replace approximately 2,500 feet of plant water pipes ranging from 4 to 10 inches in diameter.

 

Staff recommends awarding a Construction Contract contingency of 15% rather than the usual 10%.  This project will be doing work in the same areas as other construction projects and the complexity of work in congested utility tunnels often involves higher than average change order rates.

 

TIMING CONCERNS

 

If this project is delayed, spot repairs would continue to be required on an emergency basis and outages could impact treatment processes that rely on plant water. 

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Not moving forward with this project could cause the high cost and disruptive nature of emergency leak repair to continue in these areas.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

The Orange County Sanitation District (Sanitation District) advertised Project No. FE18-14 for bids on September 10, 2020 and 10 bids were received on October 20, 2020.  A summary of the bid opening follows:

 

Engineer’s Estimate                                            $1,300,000

 

Bidder                                                                   Amount of Bid

MMC Inc.                                                              $1,134,000

J.F. Shea Construction, Inc.                                 $1,149,000

Innovative Construction Solutions                        $1,149,435

Shimmick Construction Company, Inc.                $1,290,000

J.R. Filanc Construction                                       $1,317,900

PCL Construction Inc.                                          $1,385,742

Aid Builders                                                          $1,420,000

Myers & Sons Construction, LLC                         $1,459,459

Tharsos Inc.                                                         $1,576,000

Environmental Construction, Inc.                         $1,649,383

 

The bids were evaluated in accordance with the Sanitation District’s policies and procedures.  A notice was sent to all bidders on November 24, 2020 informing them of the intent of Sanitation District staff to recommend award of the construction contract to MMC Inc.

 

Staff recommends awarding a Construction Contract to the lowest responsive bidder, MMC Inc., for a total amount not to exceed $1,134,000.

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301 because the project involves repairs, replacement, and or minor alteration of existing facilities involving no expansion of use or capacity.  A Notice of Exemption will be filed with the OC Clerk-Recorder after the Sanitation District’s Board of Directors approves the Construction Contract.

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of the Sanitation District's Purchasing Ordinance.  This item has been budgeted.  (Adopted Budget, Fiscal Years 2020-2021 and 2021-22, Section 8, Page 48, Small Construction Projects Program, Project No. M-FE) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Construction Contract

 

SS:dm:sa:gc