File #: 2025-4099    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/6/2025 In control: OPERATIONS COMMITTEE
On agenda: 2/26/2025 Final action: 2/26/2025
Title: MAIN SEWAGE PUMP NO. 1 AND SPARE SEWAGE PUMP REPAIR AT PLANT NO. 2 (MP2-018), SPECIFICATION NO. S-2024-652BD
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report, 2. General Services Contract S-2024-652BD
Related files: 2025-4046

FROM:                     Robert Thompson, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance 

 

SUBJECT:

 

title

MAIN SEWAGE PUMP NO. 1 AND SPARE SEWAGE PUMP REPAIR AT PLANT NO. 2 (MP2-018), SPECIFICATION NO. S-2024-652BD

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Approve a General Services Contract to Bender CCP, Inc. to provide Main Sewage Pump No. 1 and Spare Sewage Pump Repair at Plant No. 2 (MP2-018), Specification No. S-2024-652BD, for a total amount not to exceed $999,780; and

 

B.       Approve a contingency of $99,978 (10%).

body

 

BACKGROUND

 

The Orange County Sanitation District (OC San) has seven Main Sewage Pumps (MSP) at Plant No. 2 Headworks that transfer wastewater from the Bar Screen facility to the discharge channel and grit basin.  MSP’s 1 through 3 are dedicated to non-reclaimable flows and MSP 4 through 7 are dedicated to reclaimable flows when operating in separated mode.

 

RELEVANT STANDARDS

 

                     24/7/365 treatment plant reliability

                     Maintain a proactive asset management program

                     Operate and maintain facilities to minimize impacts on surrounding communities, including odor, noise, and lighting

 

PROBLEM

 

MSP 1 is showing signs of deterioration due to worn bearings.  The Spare MSP has corrosion from prior service and requires refurbishment prior to being put into service.  It is essential that these critical pumps be in optimum condition to ensure reliability.

 

 

 

 

PROPOSED SOLUTION

 

Approve the General Services Contract to overhaul and recondition both MSP 1 and the spare pump at Plant No. 2 to Original Equipment Manufacturer specifications.  The spare MSP will be overhauled first, and upon completion it will replace MSP 1.  Subsequently, MSP 1 will be overhauled as well.

 

TIMING CONCERNS

 

Due to the criticality of these pumps to the process, MSPs must be continuously operational. 

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If the preliminary process flow to the plant fails, it could potentially cause a significant spill.  As the MSPs are split to provide influent pumping to both the non-reclaimable and reclaimable streams, it is vital to ensure that pumping capacity and redundancy is available to meet our agreement with GWRS.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

A Notice of Inviting Bids was issued on November 20, 2024, via PlanetBids.  A mandatory job walk was conducted at OC San’s Plant No. 2 on December 4, 2024.  Bids were due on December 19, 2024.  OC San received four (4) Bids which are valid for 180 calendar days from the bid opening due date.

 

Bid Results:

Company Name

Bid

Determination

Bender CCP, Inc.

$   999,780.00

Responsive/Responsible

Mehta Mechanical Company Inc.

$1,092,000.00

Responsive/Responsible

Powers Bros. Machine

$1,190,000.00

Responsive/Responsible

Innovative Construction Solutions

$1,245,000.00

N/A

 

Only the three lowest bidders were evaluated in terms of financial and safety compliance and were therefore found responsive and responsible.

 

Based on these results, staff recommends approving the General Services Contract to Bender CCP, Inc.  The term of this Contract will begin upon the effective date of the Notice to Proceed. 

 

CEQA

 

N/A

 

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget FY 2024-25 and 2025-26, Section 6, Page 112, Division 880 Plant No. 2 Maintenance, Repairs & Maintenance) and the budget is sufficient for the recommended action.

 

Date of Approval

Contract Amount

Contingency

02/26/2025

$999,780

99,978 (10%)

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     General Services Contract