Legislation Details

File #: 2026-5067    Version: 1 Name:
Type: Non-Consent Status: Final
File created: 8/19/2026 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2026 Final action:
Title: A-SIDE PRIMARY CLARIFIERS REPLACEMENT AT PLANT NO. 2, CONTRACT NO. P2-98A
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Presentation
Related files: 2021-1642

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

A-SIDE PRIMARY CLARIFIERS REPLACEMENT AT PLANT NO. 2, CONTRACT NO. P2-98A

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Approve a project budget increase of $4,400,000 for A-Side Primary Clarifiers Replacement at Plant No. 2, Contract No. P2-98A as part of Primary Treatment Rehabilitation at Plant No. 2, Project No. P2-98, for a new total budget of $193,400,000; and

 

B.       Approve a contingency increase of $1,680,000 (20%) for a new total contingency of $2,520,000 (30%) to the existing Professional Construction Services Agreement with Black & Veatch Corporation to provide construction support services for A-Side Primary Clarifiers Replacement at Plant No. 2, Contract No. P2-98A as part of Primary Treatment Rehabilitation at Plant No. 2, Project No. P2-98.

body

 

BACKGROUND

 

The primary treatment process removes solids from screened wastewater in large concrete structures called primary clarifiers.  Orange County Sanitation District (OC San) has fourteen circular primary clarifiers at Plant No. 2, constructed between 1960 and 1985, including four A-Side clarifiers constructed between 1960 and 1963 that require complete replacement.

 

OC San executed the A-Side Primary Clarifiers Replacement Project, Contract No. P2-98A, to construct four primary clarifiers, an odor control and chemical facility, an electrical distribution center, and ancillary utilities and facilities.  After the new facilities are completed, the four existing A-Side primary clarifiers, a power building, and an odor control facility will be demolished.

 

Construction began in July 2021 and is approximately 87% complete, with completion expected by late 2027.

 

RELEVANT STANDARDS

 

•                     Ensure the public’s money is wisely spent

•                     24/7/365 treatment plant reliability

 

PROBLEM

 

The existing Professional Construction Services Agreement (PCSA) with Black & Veatch Corporation for $8,400,000 was based on an assumed level of construction support services, including the number of meetings, submittal reviews, and responses to contractor requests for information. 

 

Based on that information, a contingency of $840,000 (10%) was requested and approved.  Unforeseen underground obstructions due to original Plant construction and an approximate 13-month construction schedule delay have increased the level of construction support beyond the original assumptions, nearly depleting the available PCSA authority.  The remaining PCSA authority is insufficient to provide construction support services through project completion.

 

The additional project budget beyond the PCSA contingency increase is needed for ongoing arbitration and increased project soft costs associated with the extended construction duration.  The project budget increase also provides funding to cover remaining risks and unforeseen costs through project completion.

 

PROPOSED SOLUTION

 

Approve the project budget increase to fund legal services associated with ongoing arbitration, cover additional project soft costs resulting from the extended construction duration, and fund future risks and unforeseen costs through project completion.

 

Approve the requested PCSA contingency increase of $1,680,000 (20%) over the previously approved contingency of $840,000 (10%) for a total contingency of $2,520,000 (30%) for construction support services through project completion.

 

TIMING CONCERNS

 

Delaying approval of the PCSA contingency increase could interrupt construction support services before project completion.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If the requested PCSA contingency increase is not approved, the remaining PCSA authority will be insufficient to provide the required construction support services through project completion. 

 

If the requested project budget increase is not approved, the project budget will be insufficient to fund anticipated legal services associated with arbitration and increased project soft costs resulting from the extended construction duration.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

May 2021 - Approved a Professional Construction Services Agreement with Black & Veatch Corporation to provide construction support services for A-Side Primary Clarifiers Replacement at Plant No. 2, Contract No. P2-98A, for a total amount not to exceed $8,400,000; and approved a contingency of $840,000 (10%).

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

This project is exempt from CEQA under the Class 2 categorical exemptions set forth in California Code of Regulations sections 15302 Replacement or Reconstruction of Existing Structures and Facilities.  A Notice of Exemption was filed with the Orange County Clerk-Recorder on April 26, 2018.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget FY 2026-27 and FY 2027-28, Section 8, Page 73, Primary Treatment Rehabilitation at Plant No. 2, Project No. P2-98). This item will increase the project budget and will be funded from the CIP budget.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

•                     Presentation

 

SA:lb