File #: 2025-4351    Version: 1 Name:
Type: Consent Status: Passed
File created: 6/12/2025 In control: OPERATIONS COMMITTEE
On agenda: 3/4/2026 Final action: 3/4/2026
Title: SECONDARY TREATMENT AREA CABLE REPLACEMENT AT PLANT NO. 1, PROJECT NO. FR1-0023
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. FR1-0023 Construction Contract Agreement
Related files: 2026-4829

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

SECONDARY TREATMENT AREA CABLE REPLACEMENT AT PLANT NO. 1, PROJECT NO. FR1-0023

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Receive and file Bid Tabulation and Recommendation for Secondary Treatment Area Cable Replacement at Plant No. 1, Project No. FR1-0023;

 

B.       Award a Construction Contract Agreement to Big Sky Electric, Inc., for Secondary Treatment Area Cable Replacement at Plant No. 1, Project No. FR1-0023, for a total amount not to exceed $298,102; and

 

C.       Approve a contingency of $59,600 (20%).

body

 

BACKGROUND

 

Orange County Sanitation District (OC San) operates an effluent junction box at Plant No. 1 that conveys treated effluent to the Plant No. 2 ocean outfall.  OC San also supports the Orange County Water District’s (OCWD’s) Groundwater Replenishment System (GWRS) by supplying electrical power from Power Building 8 to the GWRS Metering Vault located at Plant No. 1.  After the initial construction of the GWRS, OCWD took over the operation of the metering vault.

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

                     24/7/365 treatment plant reliability

 

PROBLEM

 

The power cable to the effluent junction box shows signs of failure and the power and control cables serving OCWD GWRS metering vault at Plant No. 1 are damaged.  The condition of these cables affects the reliability of electrical service needed to support effluent conveyance to Plant No. 2 and the transfer of flow to OCWD.

 

PROPOSED SOLUTION

 

Award a construction contract agreement to replace damaged power and control cables for the GWRS metering vault.  These cables will be fed from the adjacent OCWD screenings electrical room instead of Power Building 8.  This project will also replace power cables between the Plant No. 1 12kV Service Center and the effluent junction box.

 

TIMING CONCERNS

 

Delaying the project award increases the risk of additional power and control cable failure at the GWRS metering vault and a failure of the power cable to the effluent junction box.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If the damaged cables to the GWRS metering vault fail, OCWD will lose the flow signal to their control system and will need to manually operate the valve to control the flow from OC San’s Plant No. 1 trickling filters, and/or will need to pump out the metering vault with an external pump if it floods.  If the power cable to OC San’s effluent junction box fails, flow to Plant No. 2 will need to be manually controlled.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

OC San advertised Project No. FR1-0023 for bids on September 9, 2025, and two sealed bids were received on October 21, 2025.  A summary of the bid opening follows:

 

Engineer’s Estimate

$ 750,000

Bidder

Amount of Bid

Big Sky Electric, Inc.

$ 298,102

Minako America Corporation, dba Minco Construction

$ 877,700

 

The bids were evaluated in accordance with OC San’s policies and procedures.  A notice was sent to all bidders on February 11, 2026, informing them of the intent of OC San staff to recommend award of the Construction Contract Agreement to Big Sky Electric, Inc.  The difference between the engineer’s estimate and the contractor’s estimate was mainly due to the engineer’s estimate using higher markups, having longer generator rental durations, and over estimating subcontractor markups.

 

Staff recommends awarding a Construction Contract Agreement to the lowest responsive and responsible bidder, Big Sky Electric, Inc., for a total amount not to exceed $298,102.

 

 

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations section 15301.  A Notice of Exemption will be filed with the OC Clerk-Recorder and State Clearinghouse after OC San's Board of Directors approval of the construction contract agreement.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update FY 2025-26, Page 33, Repairs & Maintenance) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Construction Contract Agreement

 

 

AC:lb