FROM: James D. Herberg, General Manager
Originator: Kathy Millea, Director of Engineering
SUBJECT:
title
GISLER-RED HILL INTERCEPTOR REHABILITATION, PROJECT NO. 7-65
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION:
A. Approve a Professional Design Services Agreement with CDM Smith to provide engineering services for Gisler-Red Hill Interceptor Rehabilitation, Project No. 7-65, for an amount not to exceed $1,754,000; and
B. Approve a contingency of $175,400 (10%).
body
BACKGROUND
The Orange County Sanitation District (Sanitation District) owns and maintains regional conveyance facilities in the Cities of Costa Mesa and Irvine, including the 30 and 33-inch diameter Gisler-Red Hill Interceptor and the Baker Force Mains. The Gisler-Red Hill Interceptor runs approximately 15,000 feet from near Main Street Pump Station to College Avenue Pump Station near Harbor Blvd.; mostly just south of the 405 Freeway in the Cities of Costa Mesa and Irvine. The Baker Force Mains are two 42-inch diameter force mains running approximately 6,000 feet from Main Street Pump Station to Baker Street; mostly along Airway Avenue in the City of Costa Mesa. The facilities range in age from 30 to 55 years. The interceptor and force mains are not capacity deficient.
RELEVANT STANDARDS
• Achieve less than 2.1 sewer spills per 100 miles
• Protect Orange County Sanitation District assets
• California Government Code §4526: Select the “best qualified firm” and “negotiate fair and equitable fees”
PROBLEM
Condition assessments completed in 2015 and 2017 on the Gisler-Red Hill Interceptor indicate corrosion in most of the manholes, as well as multiple cracks in the vitrified clay piping. The Baker Force Mains have corrosion and liner failures due to the corrosive gas migration from the wet wells.
PROPOSED SOLUTION
Award a Professional Design Services Agreement for Gisler-Red Hill Interceptor Rehabilitation, Project No. 7-65. The project will rehabilitate the Gisler-Red Hill Interceptor and the Baker Force Mains.
TIMING CONCERNS
The schedule driver of this project is to resolve the safety and reliability risks associated with deteriorated facilities to reduce the risks of potential spills and structural failures.
RAMIFICATIONS OF NOT TAKING ACTION
Increased risk of failure of the pipes due to continued corrosion causing a sewage spill, and, potentially, property damage.
PRIOR COMMITTEE/BOARD ACTIONS
N/A
ADDITIONAL INFORMATION
Consultant Selection:
The Sanitation District requested and advertised for proposals for Gisler-Red Hill Interceptor Rehabilitation, Project No. 7-65, on May 13, 2020. The following evaluation criterion were described in the Request for Proposals (RFP) and used to determine the most qualified Consultant.
CRITERION |
WEIGHT |
Project Understanding and Approach |
35% |
Related Project Experience |
30% |
Project Team and Staff Qualifications |
35% |
Six proposals were received on June 30, 2020 and evaluated in accordance with the evaluation process set forth in Sanitation District Board of Directors’ Purchasing Ordinance No. OCSD-52 (Purchasing Ordinance) by a pre-selected Evaluation Team consisting of the Sanitation District staff: Senior Engineer (Project Manager), Associate Engineer (Project Engineer), two Engineering Supervisors, and a Maintenance Supervisor. The Evaluation Team also included one non-voting representative from the Contracts Administration Division.
The Evaluation Team scored the proposal on the established criterion as summarized in the table below:
|
Firm |
Approach (Max 40) |
Related Experience (Max 30) |
Team (Max 30) |
Total Score (Max 100) |
1 |
CDM Smith |
31 |
23 |
29 |
83 |
2 |
GHD |
20 |
14 |
17 |
51 |
3 |
Michael Baker International, Inc. |
13 |
13 |
15 |
41 |
4 |
Tetra Tech |
10 |
13 |
14 |
37 |
5 |
Lockwood, Andrews & Newnam, Inc. (LAN) |
11 |
10 |
11 |
32 |
6 |
Atkins North America, Inc. |
8 |
11 |
13 |
32 |
Following scoring, the Evaluation Team concluded that interviews were not necessary to determine the most qualified consultant. CDM Smith was selected as the most qualified Consultant based on their superior project approach and detailed understanding of the risks involved with the project. The team and related project experience directly related to rehabilitation of both gravity and force mains are well suited to the scope and likely challenges of the current project.
Review of Fee Proposal and Negotiations:
Proposals were accompanied by sealed fee proposals. Only the fee proposal of the Evaluation Committee’s highest-ranked firm, as approved by the Director of Engineering, was opened in accordance with the Purchasing Ordinance.
Staff conducted negotiations with CDM Smith to clarify the requirements of the Scope of Work, the assumptions used for the estimated level of effort, and the proposed approach to meet the goals and objectives for the project. Negotiations were held with multiple follow up e-mails and calls. The fee decreased due to project meetings being held virtually instead of in person and minor revisions of effort required by subconsultants.
|
Original Fee Proposal |
Negotiated Fee |
Total Hours |
7,099 |
6,750 |
Total Fee |
$1,971,681 |
$1,754,000 |
The Consultant’s fringe and overhead costs, which factor into the billing rate, have been substantiated. The contract profit is 7.77%, which is based on an established formula based on the Sanitation District’s standard design agreements.
Based on the above, staff has determined that the final negotiated fee is fair and reasonable for the level of effort required for this project and recommends award of the Professional Design Services Agreement to CDM Smith.
CEQA
The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Sections 15301 because the project involves repairs, replacement, and or minor alteration of existing facilities involving no expansion of use or capacity.
A Notice of Exemption will be filed with the OC Clerk-Recorder after the Sanitation District Board award of the Professional Design Services Agreement contract.
FINANCIAL CONSIDERATIONS
This request complies with authority levels of the Sanitation District's Purchasing Ordinance. This item has been budgeted. (Adopted Budget, Fiscal Year 2020-2021 and 2021-2022, Section 8, Page 33) and the project budget is sufficient for the recommended action.
ATTACHMENT
The following attachment(s) may be viewed on-line at the OCSD website (www.ocsd.com) with the complete agenda package:
• Professional Design Services Agreement
RL:dm:gc