File #: 2021-1587    Version: 1 Name:
Type: Consent Status: Passed
File created: 4/9/2021 In control: OPERATIONS COMMITTEE
On agenda: 4/28/2021 Final action: 4/28/2021
Title: PLANT BOILER SYSTEM RELIEF AT PLANT NO. 2, PROJECT NO. FE18-15
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. FE18-15 Contract Agreement & Exhibit A
Related files: 2021-1516

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

PLANT BOILER SYSTEM RELIEF AT PLANT NO. 2, PROJECT NO. FE18-15

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Receive and file Bid Tabulation and Recommendation for Plant Boiler System Relief at Plant No. 2, Project No. FE18-15;

 

B.       Award a Construction Contract to Mehta Mechanical Company, Inc., dba MMC, Inc. for a total amount not to exceed $230,000; and

 

C.       Approve a contingency of $34,500 (15%).

body

 

BACKGROUND

 

The anaerobic digesters at Plant No. 2 are used to biologically stabilize and reduce the solids produced by treating wastewater.  Under normal circumstances, the heat required to maintain biological process in the anaerobic digesters is recovered from the Central Generation engines.  When the engines or the heat recovery system are unavailable, two auxiliary steam boilers are used instead.  These two boilers have an operating permit from the South Coast Air Quality Management District that requires emissions testing every six months whether the boilers are used or not.

 

RELEVANT STANDARDS

 

                     Comply with environmental permit requirements

                     Commitment to safety & reducing risk in all operations

                     Comply with California Public Contract Code Section 20103.8, award Construction Contract to lowest responsive, responsible bidder

 

PROBLEM

 

Mandatory emissions testing for the auxiliary steam boilers requires the boilers to produce more steam than can be used, which requires the release of steam to the atmosphere.  There is, however, no provision for the safe release of steam.  To conduct the testing, staff opens a manual valve in the steam line in the tunnels.  This creates a safety issue for the person opening and closing the valve and releases a large amount of hot steam and high-pitched noise in the area.

 

PROPOSED SOLUTION

 

Award a construction contract for Plant Boiler System Relief at Plant No. 2, Project No. FE18-15.  This project will install a new steam line to a steam separator on the roof of the boiler building where steam can be safely released into the atmosphere.  The steam separator will also attenuate the noise of the released steam.

 

TIMING CONCERNS

 

Safety risks associated with the steam release to conduct the boiler emissions testing will continue until the work can be completed.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Safety risks associated with the steam release to conduct the boiler emissions testing will continue.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

The Orange County Sanitation District (OC San) advertised Project No. FE18-15 for bids on January 4, 2021 and two sealed bids were received on February 16, 2021.  A summary of the bid opening follows:

 

Engineer’s Estimate

$ 120,000

 

 

Bidder

Amount of Bid

Mehta Mechanical Company, Inc., dba MMC, Inc.

$ 230,000

ACCO Engineered Systems, Inc.

$ 236,773

 

Only two bids were received, and they were nearly double the engineer’s estimate.  Given that OC San has received many bids on some recent small contracts, the reason that only two contractors submitted bids is not clear.  The estimate had assumed a more favorable bid environment, both for construction and for materials.  The project involves a significant amount of stainless steel piping, which may be subject to high price volatility given recent supply chain uncertainties.  The closeness of the two bids suggests that the price represents the fair market value.  Given the safety driver for this project, staff believes the project is still warranted even with the higher bid price.

 

The bids were evaluated in accordance with OC San policies and procedures.  A notice was sent to all bidders on March 16, 2021 informing them of the intent of OC San staff to recommend award of the Construction Contract to Mehta Mechanical Company, Inc., dba MMC, Inc.

 

Staff recommends awarding a Construction Contract to the lowest responsive bidder, Mehta Mechanical Company, Inc., dba MMC, Inc., for a total amount not to exceed $230,000.

 

CEQA

 

This project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301 because the project involves repairs, replacement, and or minor alteration of existing facilities involving no expansion of use or capacity.  A Notice of Exemption was filed with the OC Clerk-Recorder on July 28, 2020.

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Adopted Budget, Fiscal Years 2020-2021 and 2021-22, Section 8, Page 48, Small Construction Projects Program, Project No. M-FE) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Construction Contract

 

JM:DR:dm