Skip to main content
File #: 2025-4326    Version: 1 Name:
Type: Consent Status: Reported to Board
File created: 6/4/2025 In control: OPERATIONS COMMITTEE
On agenda: 6/25/2025 Final action:
Title: SANTA ANA TRUNK SEWER REHABILITATION, PROJECT NO. 1-23
Sponsors: Mike Dorman
Attachments: 1. Union Pacific Railroad Company Agreement
Related files: 2025-4261

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

SANTA ANA TRUNK SEWER REHABILITATION, PROJECT NO. 1-23

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:

Approve an agreement with the Union Pacific Railroad Company (UPRR) for the installation and operation of a temporary, above grade, bypass pipe in the UPRR right-of-way during the construction of Santa Ana Trunk Sewer Rehabilitation, Project No. 1-23, in the amount of $373,770, in a form approved by General Counsel.

body

 

BACKGROUND

 

The Santa Ana Trunk carries sewage from the southern portion of the cities of Santa Ana and Costa Mesa to Orange County Sanitation District (OC San) Plant No. 1.  This sewer was originally constructed in the early 1950s and consists of unlined 42-inch and 48-inch diameter reinforced concrete pipes.  Over the past 60 years, several projects have replaced or rehabilitated small portions of the sewer and rehabilitated most of the manholes.

 

The project area for the Santa Ana Trunk Sewer Rehabilitation is located on Alton Avenue heading west from Bristol Street then diagonally through easements in a light industrial/commercial area toward Plant No. 1.  There is an UPRR right-of-way that runs parallel to Alton Avenue.

 

RELEVANT STANDARDS

 

                     Protect OC San assets

                     Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities

                     Maintain a culture of improving efficiency to reduce the cost to provide the current services level or standard

 

 

PROBLEM

 

To facilitate the required rehabilitation work, sewer flows along Alton Avenue must be bypassed.  In addition, several flows originating north of the UPRR tracks need to be intercepted and rerouted around the bypassed section.  The only viable route for this bypass piping is through the UPRR right-of-way.  UPRR requires an agreement to allow OC San use of their right-of-way for the bypass.

 

PROPOSED SOLUTION

 

Approve an agreement with the UPRR to allow OC San to install the needed temporary, above grade bypass pipe in the UPRR right-of-way.  This agreement, including the terms, location, and the costs, has been negotiated by staff to meet the needs of the Santa Ana Trunk Sewer Rehabilitation Project and safety requirements of the UPRR.

 

TIMING CONCERNS

 

UPRR requires the agreement to be fully executed, including payment, by September 26, 2025.  The construction project is scheduled to begin in January 2026.  Installing the bypass line in the UPRR right-of-way is required before the contractor can begin the repair work on the trunk line.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Without this agreement, bypassing of sewer flows around the UPRR right-of-way would not be possible and therefore the rehabilitation of the Santa Ana Trunk Sewer would be considerably more expensive and cause more community impacts.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

April 2022 - Approved a Professional Design Services Agreement with Stantec Consulting Services, Inc. to provide engineering services for Santa Ana Trunk Sewer Rehabilitation, Project No. 1-23, for an amount not to exceed $3,880,000; and approved a contingency of $388,000 (10%).

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

The project is exempt from CEQA under Class 1, 2, and 3 categorical exemptions set forth in California Code of Regulations Sections 15301, 15302, and 15303.  A Notice of Exemption will be filed with the OC Clerk-Recorder after OC San Board of Directors approval of the Construction Contract.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget FY 2024-25 and 2025-26, Section 8, Page 15, Santa Ana Trunk Sewer Rehabilitation, Project No. 1-23) and the budget is sufficient for the recommended action.

 

 

 

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Union Pacific Railroad Company Agreement

 

 

VP:lb