Title: PRIMARY SEDIMENTATION BASINS NO. 3-5 REPLACEMENT AT PLANT NO. 1, PROJECT NO. P1-126
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Presentation
Related files: 2022-2253

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

PRIMARY SEDIMENTATION BASINS NO. 3-5 REPLACEMENT AT PLANT NO. 1, PROJECT NO. P1-126

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

Approve a contingency increase of $849,780 (6%) to the existing Professional Design Services Agreement with Black & Veatch Corporation to provide design services for Primary Sedimentation Basins No. 3-5 Replacement at Plant No. 1, Project No. P1-126, for a total contingency not to exceed $2,266,080 (16%).

body

 

BACKGROUND

 

Primary treatment is the second of three liquid treatment steps at Orange County Sanitation District (OC San) Plant No. 1 which removes suspended solids using large concrete primary sedimentation basins.  Plant No. 1 has 26 rectangular clarifiers constructed in the 1980s and 1990s and three circular clarifiers constructed in the late 1950s and early 1960s.  Due to the current degraded condition of the circular clarifiers, they currently provide additional capacity during peak wet weather flows and when rectangular clarifiers are unavailable for maintenance or condition assessments.  The project will replace the three circular clarifiers and related primary treatment facilities to restore reliable treatment capacity.

 

RELEVANT STANDARDS

 

•                     Ensure the public’s money is wisely spent

•                     24/7/365 treatment plant reliability

 

PROBLEM

 

The original Professional Design Services Agreement included a 10% contingency to address changes to the original Scope of Work.  A significant portion of the contingency has been used to reevaluate the rehabilitation versus replacement concept, perform system-wide electrical power system studies, review updated structural code requirements, and design a new primary effluent junction box.  The new junction box reduces the need for bypass pumping during construction and provides a long-term hydraulic benefit by allowing the upstream junction box to operate at a higher water level.  This improves peak wet weather flow handling and reduces the risk of an unanticipated primary overflow.

 

The remaining contingency is insufficient to complete additional design changes, including a temporary motor control center for the existing odor control facility during construction, pipe material revisions and design changes to address liquefaction settlement risks, and design modifications around existing piles to reduce construction risks and delays.

PROPOSED SOLUTION

 

Approve the contingency increase to complete the remaining design changes needed to address temporary electrical equipment for support construction sequencing, liquefaction settlement, and existing site conditions.

 

TIMING CONCERNS

 

Delaying approval could postpone authorization of the remaining design changes and delay design completion.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Without the additional contingency, OC San would need to remove or reduce portions of the design scope to remain within the existing agreement budget.  This could require future projects to complete omitted work or increase construction risks.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

April 2022 - Approved a Professional Design Services Agreement with Black & Veatch Corporation to provide engineering services for Primary Sedimentation Basins No. 3-5 Replacement at Plant No. 1, Project No. P1-126, for an amount not to exceed $14,163,000; and approved a contingency of $1,416,300 (10%).

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

The project is exempt from CEQA under the Class 2 categorical exemptions set forth in California Code of Regulations sections 15302 Replacement or Reconstruction of Existing Structures and Facilities.  A Notice of Exemption was filed with the OC Clerk-Recorder on April 29, 2022.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget FY 2026-27 and FY 2027-28, Section 8, Page 50, Primary Sedimentation Basins No. 3-5 Replacement at Plant No. 1, Project No. P1-126.  This item will be funded from the CIP budget.

 

 

Date of Approval

Contract Amount

Contingency

04/22/2022 10/28/2026

$ 14,163.000

$ 1,416,300 (10%) $    849,780 (6%)

 