File #: 2024-3650    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 6/6/2024 In control: OPERATIONS COMMITTEE
On agenda: 6/26/2024 Final action: 6/26/2024
Title: SUNFLOWER PUMP REPLACEMENT AT PLANT NO. 1, PROJECT NO. FE19-04
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Presentation - FE19-04 Sunflower Contingency Increase
Related files: 2024-3640

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

SUNFLOWER PUMP REPLACEMENT AT PLANT NO. 1, PROJECT NO. FE19-04

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

Approve a contingency increase of $318,480 (15%) to the construction contract with GSE Construction Company Inc. for Sunflower Pump Replacement at Plant No. 1, Project No. FE19-04, for a total construction contingency of $530,800 (25%).

body

 

BACKGROUND

 

The Orange County Sanitation District (OC San) Sunflower Pump Station transfers flows into Headworks from the deepest of the trunk sewers feeding Plant No. 1.  The pump station uses two 40million gallon per day screw pumps to lift flow from the Sunflower Trunk into Plant No. 1.  The screws for those pumps are approximately 32 feet long, have a 9-foot diameter, and are driven through a large gearbox to reduce the speed of the 150-horsepower motor down to 28 revolutions per minute.  These pumps are subject to erosion of the screws, corrosion from the sewer gas, and wear and tear on bearings submerged in wastewater.

 

RELEVANT STANDARDS

 

                     Protect OC San assets

                     Maintain a proactive asset management program

                     24/7/365 treatment plant reliability

 

PROBLEM

 

The original contract included the replacement of the Pump 1 screw pump and the replacement of the grout and polyurethane coating in the trough area underneath the pump.  During the removal of the screw pump, the contractor discovered extensive damage to the concrete and coating in the area above the trough, which is not part of the project scope.  In addition, during construction it was discovered that an existing control and signal duct bank for the screw pumps is not correctly shown on existing as-built drawings and interferes with a future stairway constructed for the existing Metering and Diversion Structure by Project No. P1-105, Headworks Rehabilitation at Plant No. 1, and needs to be rerouted.  Replacing these interfering cables and conduits under this project will eliminate a future pump outage.

 

PROPOSED SOLUTION

 

Approve a contingency increase of $318,480 to repair the concrete and coating system above the trough for Pump 1 and replace the existing control and signal cables and conduits to both screws pumps, which are outside the current scope of work.  This will provide sufficient contingency for contract work.

 

TIMING CONCERNS

 

Pump 1 is currently being replaced by this project.  It is critical that the work on Pump 1 continue without interruption so it can be returned to service prior to the start of the wet weather season in October to provide sufficient pumping capacity.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Pump 1 will need to be put back into service without the repairs.  The repair work will need to be done under a future project, resulting in increased repair costs to remove the screw pump to perform the repairs.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

October 2021 - Awarded a Construction Contract to GSE Construction Company Inc. for Sunflower Pump Replacement at Plant No. 1, Project No. FE19-04, for a total amount of not to exceed $2,123,200; and approved a contingency of $212,320 (10%).

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update, Fiscal Year 2023-2024, Appendix A, Page 8, Small Construction Projects Program, Project No. M-FE) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Presentation