File #: 2021-1828    Version: 1 Name:
Type: Consent Status: Passed
File created: 8/25/2021 In control: OPERATIONS COMMITTEE
On agenda: 10/6/2021 Final action: 10/6/2021
Title: PLANT NO. 1 BUILDING A FEEDER CABLES REPLACEMENT (MP-337)
Sponsors: Rob Thompson
Attachments: 1. Agenda Report, 2. S-2021-1261BD Draft Service Contract and SOW
Related files: 2021-1894

FROM:                     James D. Herberg, General Manager

                     Originator: Rob Thompson, Assistant General Manager 

 

SUBJECT:

 

title

PLANT NO. 1 BUILDING A FEEDER CABLES REPLACEMENT (MP-337)

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Approve a Service Contract to AMTEK Construction for P1 Building A Feeder Cables Replacement (MP-337), for 480V feeder cables, per Specification No. S-2021-1261BD, for a total amount not to exceed $356,333; and

 

B.       Approve a contingency of $35,633 (10%).

body

 

BACKGROUND

 

Plant No. 1 Maintenance Building A houses the rebuild shop support facilities and equipment.  The rebuild shop is a support function of the Orange County Sanitation District (OC San) where major mechanical equipment such as pumps, valves, and structural components are rebuilt or fabricated.  Electrical power to Building A is fed from a power building located within Plant No. 1.

 

RELEVANT STANDARDS

 

                     Protect OC San assets

                     24/7/365 treatment plant reliability

                     Maintain a proactive asset management program

 

PROBLEM

 

Routine predictive maintenance testing discovered that the insulation on the feeder cables for Plant No. 1 Maintenance Building A is failing.  The cable was taken out of service to prevent a catastrophic cable failure.

 

PROPOSED SOLUTION

 

Replace existing feeder cables to restore full utility to the rebuild shop facilities.

 

 

TIMING CONCERNS

 

Proceeding in a timely fashion is recommended to prevent operational disruption and delays.  Currently, the rebuild shop is running with a lower capacity temporary arrangement using the remaining parallel conductors of the original feed.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Not acting will impact the ability of the rebuild shop to overhaul and repair plant assets.  There is also a potential for a prolonged outage due to catastrophic cable failure of the remaining cable system.  Catastrophic cable failures can damage additional equipment and create more expensive emergency repair situations.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

OC San advertised for bids on July 21, 2021.  Four sealed bids were received on August 24, 2021.  The bids were evaluated in accordance with OC San’s policies and procedures.  Staff recommends awarding a Service Contract to the lowest responsive and responsible bidder, AMTEK Construction.

 

Summary information on the bid opening is as follows:

 

Bidder

Amount of Bid

AMTEK Construction

$356,333

Eco Energy Solution, Inc. dba High Volt Electric

$481,589

Baker Electric

$586,675

M. Brey Electric, Inc.

$617,130

 

A contingency of 10% is recommended because of the potential of additional repairs discovered during removal and installation of ancillary or adjacent cabling.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of the OC San’s Purchasing Ordinance.  This recommendation will be funded under the Repair and Maintenance line item for Plant No. 1 Operations and Maintenance Department (Budget Update - Fiscal Year 2021-2022, Page 45).  The available funding is sufficient for this action.

 

 

 

Date of Approval

            Contract Amount

                           Contingency

    10/27/2021

                   $356,333

                          $35,633 (10%)

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Service Contract

 

RM:jg:my:nb:ab