FROM: Robert Thompson, General Manager
Originator: Lorenzo Tyner, Assistant General Manager
SUBJECT:
title
PROPOSED ORDINANCE ADOPTING CAPITAL FACILITIES CAPACITY CHARGES
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION:
A. Motion to read Ordinance No. OC SAN-59 by title only and waive reading of said entire Ordinance;
B. Introduce Ordinance No. OC SAN-59 entitled, “An Ordinance of the Board of the Orange County Sanitation District Adopting Capital Facilities Capacity Charges, and Repealing Ordinance No. OCSD-57”; and
C. Set March 22, 2023 as the date of the Public Hearing to hear protests and for the second reading of Ordinance No. OC SAN-59.
body
BACKGROUND
The Capital Facilities Capacity Charge (CFCC) is a one-time, non-discriminatory charge imposed at the time a building or structure is newly connected to Orange County Sanitation District’s (OC San) system, or an existing structure is expanded or increased. This charge is to pay a portion of the capacity costs and for access to capacity in the system. Based upon the rate study conducted by HDR Engineering, Inc., the Facilities Master Plan, forecasted operating expenses, and cash flow modeling, staff recommends the 3-bedroom base rate for the residential CFCC remain unchanged for Fiscal Year (FY) 2023-24 at $5,719 and will adjust by the Engineering News Record Construction Cost Index each year thereafter.
The non-residential CFCC schedule for FY 2023-24 will decrease by 33% and will adjust by the Engineering News Record Construction Cost Index each year thereafter.
Use Category |
FY 2023-24* |
Low Demand |
$ 242 |
Average Demand |
$1,485 |
High Demand |
$3,521 |
*per thousand square feet
The Supplemental Capital Facilities Capacity Charges (SCFCC) are fees to Industrial Permittees that exceed their annual baselines for Flow, Biochemical Oxygen Demand (BOD), and Total Suspended Solids (TSS). Flow and BOD will adjust by the Engineering News Record Construction Cost Index each year after FY 2023-24. The schedule for TSS is below.
|
FY 2023-24 |
FY 2024-25 |
FY 2025-26 |
FY 2026-27 |
FY 2027-28 |
FLOW |
$0.002140 |
ENR |
ENR |
ENR |
ENR |
BOD |
$0.500630 |
ENR |
ENR |
ENR |
ENR |
TSS |
$0.303640 |
$0.336440 |
$0.369240 |
$0.402040 |
$0.434930 |
FLOW - Gallons Per Day
BOD - Pounds Per Day
TSS - Pounds Per Day
RELEVANT STANDARDS
• Stable rates, no large unforeseen rate increases
PROBLEM
OC San’s Board of Directors approved a five-year rate schedule for Capital Facilities Capacity Charges which expires at the end of the current fiscal year.
PROPOSED SOLUTION
Adopt an Ordinance with updated fee schedules based upon the 2022 Rate Study performed by HDR Engineering, Inc. and received and filed by the Board in December 2022.
TIMING CONCERNS
February 22, 2023 - First Reading of the Ordinance
March 22, 2023 - Public Hearing, Second Reading, and Adoption of the Ordinance
July 1, 2023 - Ordinance takes effect
RAMIFICATIONS OF NOT TAKING ACTION
Revenues will be insufficient to support the Facilities Master Plan adopted in December 2017.
PRIOR COMMITTEE/BOARD ACTIONS
December 2022 - Received and filed the Orange County Sanitation District’s 2022 Wastewater Rates, Fees, and Charges Study completed by HDR Engineering, Inc.
July 2021 - Adopted Ordinance No. OCSD-57.
December 2017 - Approved the 2017 Facilities Master Plan and Rate Study.
ADDITIONAL INFORMATION
To ensure the appropriate allocation of costs and fees, OC San engaged an engineering consulting firm, HDR Engineering, Inc., to provide an independent analysis of OC San’s cash flow modeling and a cost of service study. The study demonstrates that OC San’s proposed fees are appropriate and reasonable and will support its projected capital and operating requirements.
CEQA
N/A
FINANCIAL CONSIDERATIONS
This request complies with authority levels of OC San’s Purchasing Ordinance. This item has been budgeted.
ATTACHMENT
The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:
• Ordinance No. OC SAN-59 (Redlined)
• Ordinance No. OC SAN-59 (Clean)