File #: 2022-2519    Version: 1 Name:
Type: Consent Status: Passed
File created: 9/8/2022 In control: OPERATIONS COMMITTEE
On agenda: 9/28/2022 Final action: 9/28/2022
Title: COLLECTION SYSTEM CONDITION MONITORING SERVICE
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report
Related files: 2022-2468

FROM:                     James D. Herberg, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance 

 

SUBJECT:

 

title

COLLECTION SYSTEM CONDITION MONITORING SERVICE

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

Approve a contingency increase of $17,777 (10%) to an existing five-year Service and Monitoring Purchase Order Agreement (107432-OB) of $177,778 with Hadronex, Inc. dba SmartCover Systems for field device communication and monitoring services, for a new total contingency of $35,554 (20%).

body

 

BACKGROUND

 

The SmartCover Systems devices are deployed in the Orange County Sanitation District (OC San) collection system at critical locations.  These locations are monitored in real-time for water level changes and hydrogen sulfide gas generation.  Staff is alerted when undesirable conditions arise and responds to rectify the situation.  Additionally, these monitors are employed for hydrogen sulfide gas generation monitoring to determine the optimal chemical dosing rates and locations for odor and corrosion suppression.

 

In December 2021, the Board of Directors approved a Service and Monitoring Purchase Order Agreement to SmartCover Systems for a total amount not to exceed $177,778 and a contingency of $17,777 (10%).  The term covers a five-year period through September 30, 2026, to remotely monitor sewer conditions, potential sewer overflows, and hydrogen sulfide gas generation in the collection system.

 

RELEVANT STANDARDS

 

                     Protect OC San assets

                     Achieve less than 2.1 sewer spills per 100 miles

                     12 or fewer odor complaints per year under normal operating conditions in the collection system

 

 

 

 

PROBLEM

 

The current agreement authorization of funds is insufficient to cover the price increase associated with additional units that are requested.  The cost of $29,803.62 for five additional units exceeds the original contingency amount approved for this purpose.  It is also anticipated that additional units need to be installed for monitoring in other locations in the collection system, which require additional funding.  Service renewal costs for the additional units have increased beyond what the original contingency of 10% can cover.

 

PROPOSED SOLUTION

 

Approve an additional contingency of 10% to cover the costs of added units to increase monitoring coverage and prevent service interruptions.

 

TIMING CONCERNS

 

A service interruption will occur if no action is taken to add funding for the additional monitoring units. 

 

RAMIFICATIONS OF NOT TAKING ACTION

 

The resulting service interruption will lead to the inability to monitor these locations for potential sewer spills and excessive hydrogen sulfide gas generation.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

December 2021 - Approved a Five-Year Service and Monitoring Purchase Order Agreement with Hadronex, Inc dba SmartCover Systems for field device communication and monitoring services, for the total amount of $177,778 billed in annual installments; and approved a contingency of $17,777 (10%).

 

ADDITIONAL INFORMATION

 

The additional five units requested are not in the scope of the original service agreement for thirty-one units with SmartCover Systems.  Staff identified the additional locations based on a need to monitor field conditions and mitigate sewer spill risk and excessive chemical use.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San's Purchasing Ordinance.  This budgeted recommendation is in the FY2022-2023 Budget, Operations and Maintenance Department, Division 820, Repairs and Maintenance line item, Operating Expense, Section 6 Page 72.  The available funding is sufficient for this action.

 

 

 

Date of Approval

Contract Amount

Contingency

12/01/2021

$177,778

$17,777 (10%)

09/28/2022

 

$17,777 (10%)

 

ATTACHMENT

The following attachment(s) may be viewed online at the OC San website (www.ocsan.gov) with the complete agenda package:

 

N/A