File #: 2024-3498    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/15/2024 In control: OPERATIONS COMMITTEE
On agenda: 3/6/2024 Final action: 3/6/2024
Title: NEWPORT BEACH PUMP STATION PRESSURIZATION IMPROVEMENTS, PROJECT NO. 5-68
Sponsors: Mike Dorman
Attachments: 1. Agenda Report
Related files: 2023-2785, 2024-3516

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering

 

SUBJECT:

 

title

NEWPORT BEACH PUMP STATION PRESSURIZATION IMPROVEMENTS, PROJECT NO. 5-68

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

Approve a contingency increase of $65,625 (7%) to the existing construction contract with Innovative Construction Solutions for Newport Beach Pump Station Pressurization Improvements, Project No. 5-68, for a total contract amount not to exceed $937,500; and a total construction contingency of $159,375 (17%).

body

 

BACKGROUND

 

The Orange County Sanitation District (OC San) owns and operates eight pump stations in the city of Newport Beach.  Six of these pump stations (Bitter Point, Crystal Cove, A Street, 15th Street, Lido, and Rocky Point) have inadequate venting for the wet wells, which can lead to the escape of odorous and corrosive gasses.  This project will install passive air scrubbers to treat the foul air to below nuisance levels before releasing the air into the atmosphere.  The project will also add a concrete slab and electrical conduits to accommodate a future chemical addition at the 15th Street Pump Station to reduce generation of hydrogen sulfide in downstream force mains.  A construction contract was awarded to Innovative Construction Solutions in February 2023 to incorporate these modifications.  The project is approximately 70% complete.

 

RELEVANT STANDARDS

 

                     Ensure the public’s money is wisely spent

                     Commitment to safety & reducing risk in all operations

                     Operate and maintain facilities to minimize impacts on surrounding communities, including odor, noise, and lighting

 

PROBLEM

 

During the course of construction, an unforeseen change was required to revise the odor scrubber design for the Bitter Point Pump Station, resulting in additional scrubber units and materials.  This change order consumed approximately $60,000 of the total construction contract contingency of $93,750.  Additional change orders have resulted in a current remaining contingency of less than $13,000.  The remaining contingency is anticipated to be insufficient to cover potential unknown construction change orders for the remainder of the construction duration.

 

PROPOSED SOLUTION

 

Approve a contingency increase of $65,625 (7%) to the construction contract for a total contingency of $159,375 (17%).  This increase will provide additional funds in the event of additional necessary changes for unknown conditions.

 

TIMING CONCERNS

 

The project is currently in construction and is close to exhausting the original contingency amount.  Additional contingency funds are requested to authorize future change orders if required to complete the remaining construction activities without incurring contractor delay costs.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If the contract contingency is not increased, it is anticipated that the project may not have sufficient funds for future unknown change orders, which would bring the project to a halt until additional funding is approved.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

February 2023 - Approved a Construction Contract to Innovative Construction Solutions for Newport Beach Pump Station Pressurization Improvements, Project No. 5-68, for an amount not to exceed $937,500; and approved a contingency of $93,750 (10%).

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

The Project is included in the Facilities Master Plan 2020 Program Environmental Impact Report, State Clearinghouse Number 2019070998.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update, Fiscal Year 2023-2024, Appendix A-7, Capital Improvement Program, Project No. 5-68) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

N/A