Legislation Details

File #: 2026-5199    Version: 1 Name:
Type: Consent Status: Final
File created: 11/12/2026 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2026 Final action:
Title: PLANT NO. 2 SPARE PLANT WATER PUMP
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report

FROM:                     Robert Thompson, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance 

 

SUBJECT:

 

title

PLANT NO. 2 SPARE PLANT WATER PUMP

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Approve a Sole Source Purchase Order to G3 Engineering, Inc. for the purchase of one Floway Pump for Plant No. 2 Spare Plant Water Pump for a total amount not to exceed $209,958 plus applicable sales tax and freight charges; and

 

B.       Approve a contingency of $20,996 (10%).

body

 

BACKGROUND

 

The Plant Water Pump Station at Orange County Sanitation District (OC San)  Plant No. 2 operates four Floway vertical turbine pumps installed under Project No. J-117B.  The station distributes treated water throughout the plant, including cooling water for the Central Generation (CenGen) system, supporting critical plant processes and maintenance activities.

 

RELEVANT STANDARDS

 

•                     24/7/365 treatment plant reliability

•                     Protect OC San assets

•                     Maintain a proactive asset management program

 

PROBLEM

 

OC San does not currently have a spare plant water pump.  Failure of an existing pump could result in extended downtime due to the 26-week replacement lead time, potentially impacting CenGen cooling and other critical plant operations.

 

PROPOSED SOLUTION

 

Purchase one spare Floway Pump for plant water through G3 Engineering, Inc., the identified authorized distributor, to maintain equipment reliability and minimize downtime following a pump failure.

 

TIMING CONCERNS

 

The replacement pump has an estimated 26-week delivery lead time.  Delaying procurement increases the risk of prolonged equipment downtime if an existing pump fails.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Without an available spare, a pump failure could result in prolonged equipment downtime, reduced plant water system reliability, and potential interruptions to CenGen cooling and other critical plant processes.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

G3 Engineering, Inc. is identified as the sole distributor for Floway Pump products in California.  A 10% contingency is requested to address potential price changes, ordering delays, or other unforeseen costs.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance.  This item has been transferred from budgeted items Primary clarifier critical spare drive C60 and Upgraded high torque motor and gearboxes only Putzmeister (Budget FY 2026-27, Section 8, Pages 82 and 87, 880-Plant No. 2 Maintenance), and the budget is sufficient for this action.

 

Date of Approval

Contract Amount

Contingency

12/02/2026

$209,958

$20,996

 

ATTACHMENT

The following attachment(s) may be viewed online at the OC San website (www.ocsan.gov) with the complete agenda package:

 

N/A