FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance
SUBJECT:
title
PLANT NO. 2 SPARE BAR SCREEN CARRIAGE ASSEMBLY
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION: Recommend to the Board of Directors to:
A. Approve a Sole Source Purchase Order to Veolia WTS Services USA Inc., for the purchase of one spare bar screen carriage assembly for a total amount not to exceed $268,168 plus applicable sales tax & freight charges; and
B. Approve a contingency of $26,817 (10%).
body
BACKGROUND
Orange County Sanitation District (OC San) Plant No. 2 utilizes mechanical bar screens at the Headworks Facility to remove debris and large solids from incoming wastewater, protecting downstream treatment equipment and maintaining reliable plant operations. The bar screen carriage assemblies use mechanical rakes to remove accumulated debris and maintain wastewater flow.
Plant No. 2 also operates in a split-mode configuration, utilizing three designated bar screens to process wastewater for the Groundwater Replenishment System (GWRS). Maintaining sufficient bar screen availability is essential to supporting split-mode operations and meeting GWRS water quality requirements.
RELEVANT STANDARDS
• 24/7/365 treatment plant reliability
• Protect OC San assets
• Protect public safety
• Maintain a proactive asset management program
PROBLEM
OC San does not currently have a spare bar screen carriage assembly. A failure requiring replacement could result in extended equipment downtime due to the 18-week fabrication lead time, potentially disrupting split-mode operations and reducing treatment flexibility.
PROPOSED SOLUTION
Procure one spare bar screen carriage assembly from the Original Equipment Manufacturer (OEM), Veolia WTS Services USA, Inc., to minimize equipment downtime and maintain operational reliability.
TIMING CONCERNS
The replacement carriage assembly requires approximately 18 weeks for fabrication and delivery. Delaying procurement increases the risk of prolonged equipment downtime and potential interruptions to GWRS split-mode operations.
RAMIFICATIONS OF NOT TAKING ACTION
Failure of a bar screen carriage assembly without an available spare could result in extended equipment downtime, reduced operational flexibility, and increased risk of interruptions to GWRS operations and regulatory noncompliance.
PRIOR COMMITTEE/BOARD ACTIONS
November 2024 - Received and filed Orange County Sanitation District Purchases made under the General Manager’s authority for the period of July 1, 2024 to September 30, 2024 and approved the following additions to the pre-approved Original Equipment Manufacturers (OEM) Sole Source List: Rockwell Engineering & Equipment Co - Horizontal Pump (Replaces OEM Manufacturer Vaughan Company, Inc. - Designated Representative) and Veolia WTS Services USA, Inc. - Bar Screen Repair Parts (Replaces OEM Manufacturer Suez WTS/Veolia WTS - Name Change).
ADDITIONAL INFORMATION
N/A
CEQA
N/A
FINANCIAL CONSIDERATIONS
This request complies with authority levels of the OC San’s Purchasing Ordinance. This recommendation will be funded under the Repair and Maintenance line item for Plant No. 2 Maintenance Department (Budget FY 2026-27, Section 8, Pages 82 and 87, 880-Plant No. 2 Maintenance). The available funding is sufficient for this action.
|
Date of Approval |
Contract Amount |
Contingency |
|
12/16/2026 |
$268,168 |
$26,817 |
ATTACHMENT
The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:
N/A