File #: 2022-2619    Version: 1 Name:
Type: Consent Status: Passed
File created: 11/2/2022 In control: OPERATIONS COMMITTEE
On agenda: 6/7/2023 Final action: 6/7/2023
Title: INFLUENT PUMP STATION PLANT WATER PIPING REPAIR AT PLANT NO. 2, PROJECT NO. FR2-0029
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. FR2-0029 Contract Agreement

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

INFLUENT PUMP STATION PLANT WATER PIPING REPAIR AT PLANT NO. 2, PROJECT NO. FR2-0029

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Receive and file Bid Tabulation and Recommendation for Influent Pump Station Plant Water Piping Repair at Plant No. 2, Project No. FR2-0029;

 

B.       Award a Construction Contract to W.A. Rasic Construction Company, Inc. for Influent Pump Station Plant Water Piping Repair at Plant No. 2, Project No. FR2-0029, for a total amount not to exceed $177,063; and

 

C.       Approve a contingency of $35,400 (20%).

body

 

BACKGROUND

 

The Orange County Sanitation District’s (OC San) Headworks Bar Screen Facility provides vital preliminary treatment to all incoming wastewater by removing trash and debris that would otherwise damage downstream treatment equipment.  Water is supplied from the adjacent Influent Pump Station and used in the sluiceways to remove and transport the debris from the bar screens for disposal.  Plant No. 2 Headworks was constructed in 2012 under Project No. P2-66, Headworks at Plant No. 2.

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

                     24/7/365 treatment plant reliability

 

PROBLEM

 

An 8-inch pipeline supplies water to the Influent Pump Station, which then supplies water to the bar screen sluiceways through two 6-inch pipelines.  The 8-inch and one of the 6-inch pipelines have failed.  The facility is currently relying on a temporary supply line and a 6-inch pipeline.

 

PROPOSED SOLUTION

 

Award a construction contract for Influent Pump Station Plant Water Piping Repair at Plant No. 2, Project No. FR2-0029.  This project will replace existing, failed underground sections of pipe to provide reliable sluice water to the Bar Screen Facility.

 

Due to the unknown location of reinforcement steel in the building walls, adjustments to pipe routing may be required to find suitable points of penetration into the building during construction.  Because of the relatively small construction value and additional work that may arise if the penetration locations must be changed, staff is requesting a higher than usual contingency of 20%.

 

TIMING CONCERNS

 

The remaining 6-inch pipe is at a high risk of failure due to the failure of multiple other pipes in the area over time.  A delay in replacing existing sections of pipe would increase the chance of failure of the in-service pipe.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Failure of the single remaining 6-inch water supply to the bar screen sluiceways would impact the ability to clear debris, potentially impacting flow into headworks.  An emergency response would be needed to manually remove the debris until temporary pipe repairs are performed.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

OC San advertised Project No. FR2-0029 for bids on February 7, 2023 and six sealed bids were received on March 23, 2023.  A summary of the bid opening follows:

 

Engineer’s Estimate

$ 225,000*

Bidder

Amount of Bid

W.A. Rasic Construction Company, Inc.

$ 177,063

Innovative Construction Solutions

$ 188,500

RE Chafee Construction Inc.

$ 196,800

Vicon Enterprise

$ 210,000

Arnaz Engineering Contractors, Inc.

$ 247,500

Mehta Mechanical Company dba MMC Inc.

$ 344,000

 

*The engineer's estimate correctly calculated the individual costs, but incorrectly summed up the total costs, resulting in a lower published engineer’s estimate of $142,000.  The corrected engineer's estimate is $225,000.

 

 

The bids were evaluated in accordance with OC San’s policies and procedures.  A notice was sent to all bidders on May 17, 2023 informing them of the intent of OC San staff to recommend award of the Construction Contract to W.A. Rasic Construction Company, Inc.

 

Staff recommends awarding a Construction Contract to the lowest responsive and responsible bidder, W.A. Rasic Construction Company, Inc., for a total amount not to exceed $177,063.

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301.  A Notice of Exemption will be filed with the OC Clerk-Recorder after OC San Board of Directors approval of the construction contract.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This recommendation would be funded under the Repairs and Maintenance line item for Division 880, Plant No. 2 Maintenance (Adopted Budget, Fiscal Years FY 2022-2023 and 2023-2024, Section 6, Page 96), and the available funding is sufficient for this action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Construction Contract

 

BT:tk