Legislation Details

File #: 2026-4837    Version: 1 Name:
Type: Non-Consent Status: Final
File created: 3/9/2026 In control: OPERATIONS COMMITTEE
On agenda: 9/2/2026 Final action:
Title: SIPHON ASSESSMENTS IN ANAHEIM, NEWPORT BEACH, AND ORANGE, PROJECT NO. PS25-01
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. PS25-01 PSA, 3. Presentation - PS25-01 PSA

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

SIPHON ASSESSMENTS IN ANAHEIM, NEWPORT BEACH, AND ORANGE, PROJECT NO. PS25-01

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Find that the recommended action is exempt from the California Environmental      Quality Act (CEQA) under the Class 6 categorical exemption set forth in CEQA Guidelines Section 15306, Information Collection, and the statutory exemption set forth in CEQA Guidelines Section 15262, Feasibility and Planning Studies;

 

B.       Approve a Professional Services Agreement with HDR Engineering, Inc., to provide engineering services for the Siphon Assessments in Anaheim, Newport Beach, and Orange, Project No. PS25-01, for an amount not to exceed $2,781,000; and

 

C.      Approve a contingency of $278,100 (10%).

body

 

 

BACKGROUND

 

The Orange County Sanitation District (OC San) collections system includes 82 inverted siphons ranging from 8-inch to 96-inch in diameter. Inverted siphons are gravity sewers that have a dip in grade to avoid conflicts with existing infrastructure. This lowered elevation results in the sewer being completely full during operation, creating more challenges than typical gravity sewers with operation, maintenance, inspection and assessment. Many of the inverted siphons are on frequent cleaning schedules to maintain operations; however, none are on a routine inspection schedule.

 

 

RELEVANT STANDARDS

 

                     Protect OC San assets

                     Maintain a proactive asset management program

                     Commitment to safety & reducing risk in all operations

 

 

PROBLEM

 

The condition of most of OC San’s inverted siphons is based on age and type of piping material versus actual condition.  Without condition information it is not feasible to accurately plan for the appropriate scope and schedule of the rehabilitation and replacement work to maintain their operation.

 

PROPOSED SOLUTION

 

Conduct a Planning Study to assess the condition of seven inverted siphons in Anaheim, Newport Beach, and Orange, evaluate their remaining useful life, develop recommendations for appropriate rehabilitation and capital improvements, and provide best practice recommendations for future siphon work.

 

TIMING CONCERNS

 

If not assessed, the siphons will continue to age and the likelihood of developing an unknown defect will increase over time.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If the inverted siphons are not assessed, potential defects will not be identified. The repair timing for these siphons will be based strictly on age versus the actual condition, making the asset management process less efficient.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

Consultant Selection:

OC San requested and advertised for proposals for the Siphon Assessments in Anaheim, Newport Beach, and Orange Study, Project No. PS25-01 on March 10, 2026.  The following evaluation criteria were described in the Request for Proposals (RFP) and used to determine the most qualified Consultant.

 

CRITERION

WEIGHT

Project Understanding and Approach

40%

Related Project Experience

35%

Project Team and Staff Qualifications

25%

 

Four proposals were received on May 5, 2026, and evaluated in accordance with the evaluation process set forth in OC San’s Purchasing Ordinance, OC SAN-61, by a pre-selected Evaluation Team consisting of the following OC San staff: Engineering Supervisor, Engineer, Assistant Engineer, and Maintenance Superintendent.

The Evaluation Team also included one non-voting representative from the Contracts Administration Division.

 

The Evaluation Team scored the proposal on the established criteria as summarized in the table below:

 

 

Firm

Approach (Max 40)

Related Experience (Max 35)

Team                 (Max 25)

Total Score (Max 100)

1

HDR Engineering, Inc.

34

31

21

86

2

Black & Veatch Corporation

32

27

20

79

3

Hazen and Sawyer

30

25

18

73

4

Murgreen Environmental Company

21

18

14

53

 

Based on the evaluation results, there was a clear natural break in the scores between the highest scoring proposer and the other proposers; therefore, the Evaluation Team did not deem it necessary to conduct interviews.

 

The selected team, HDR Engineering, Inc., presented a well-defined approach and demonstrated understanding of the scope of work, with exhibits identifying their approach for all siphon locations.  Their proposal also demonstrated a strong familiarity with different inspection technologies and an understanding of the factors that must be considered when evaluating each siphon.  In addition, their technical proposal was well written and showed a good understanding of OC San’s expectations and the effort required to prepare a successful planning study.  Furthermore, the experience of the proposed team aligns with the needs of the project, was well organized, and appropriately sized for the scope.

 

Review of Fee Proposal and Negotiations:

Proposals were accompanied by sealed fee proposals.  In accordance with the Purchasing Ordinance, the fee proposal of only the highest-ranked firm was opened after the Director of Engineering approved the Evaluation Committee’s recommendation.

 

Staff conducted negotiations with HDR Engineering, Inc., to clarify the requirements of the scope of work, the assumptions used for the estimated level of effort, and the proposed approach to meet the goals and objectives for the project. These discussions occurred over three negotiation meetings with the main outcome listed below:

 

The level of effort was reduced by removing an unproven inspection tool that was redundant for the needed work, assumptions were updated regarding the quantity of debris and the expected work hours during cleaning efforts, and meeting hours were increased:

 

 

Original Fee Proposal

Negotiated Fee

Total Hours

3,146

3,126

Total Fee

$2,838,391

$2,781,000

 

The Consultant’s fringe and overhead costs, which factor into the billing rate, have been substantiated.  The contract profit is 9.07%, which is based on OC San’s established formula for standard design agreements.

 

Based on the above, staff has determined that the final negotiated fee is fair and reasonable for the level of effort required for this project and recommends award of the Professional Services Agreement to HDR Engineering, Inc.

 

CEQA

 

The recommended action has been reviewed in accordance with the California Environmental Quality Act (CEQA).  Staff has determined that the Project Study is exempt from CEQA under Class 6 categorical exemption set forth in California Code of Regulations Section 15306, Information Collection; and statutory exemption set forth in CEQA Guidelines Section 15262, Feasibility and Planning Studies.

 

A Notice of Exemption will be filed with the OC Clerk-Recorder and submitted to the State Clearinghouse within five working days after OC San's Board of Directors approval of the Professional Services Agreement.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget FY 2026-27 and 2027-28, Section 6, Page 80, Other) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Professional Services Agreement

                     Presentation