File #: 2024-3487    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/13/2024 In control: OPERATIONS COMMITTEE
On agenda: 3/6/2024 Final action: 3/6/2024
Title: PRIMARY EFFLUENT PUMP STATION PUMP #3 REBUILD AT PLANT NO. 1
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report
Related files: 2024-3517

FROM:                     Robert Thompson, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance

 

SUBJECT:

 

title

PRIMARY EFFLUENT PUMP STATION PUMP #3 REBUILD AT PLANT NO. 1

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Approve additional funds of $244,601 to Sole Source Purchase Order 161427-OS, to DXP Enterprises, Inc. (formerly Cortech Engineering, Inc.), to rebuild Primary Effluent Pump Station Pump #3 at Plant No. 1, for a new total amount not to exceed $322,061; and

 

B.       Approve a contingency of $32,206 (10%).

body

 

BACKGROUND

 

Orange County Sanitation District (OC San) Plant No. 1 Primary Effluent Pump Station (PEPS) has three vertical pumps that were installed during Project No. P1-16 in 1973.  Primary effluent is pumped through Primary Sedimentation Basins to the secondary treatment at the activated sludge facility, AS-1, at Plant No. 1.  Additional flows that enter the PEPS wet well include Central Generation cooling water, plant water strainers, and dissolved air flotation thickeners.

 

RELEVANT STANDARDS

 

                     24/7/365 treatment plant reliability

                     Comply with environmental permit requirements

                     Maintain a proactive asset management program

                     Operate and maintain facilities to minimize impacts on surrounding communities, including odor, noise, and lighting

 

PROBLEM

 

PEPS Pump No. 3 has been operating at a diminishing output and requires overhaul.  As a result, primary effluent flow capacity is limited to Secondary Basins for treatment.  The pump was shipped to the service facility and torn down for diagnosis under a purchase order contract.  This diagnosis revealed the need for additional parts and rework than what was anticipated, including a new impeller which must be cast and machined to original specifications.

 

PROPOSED SOLUTION

 

Approve an additional $244,601 to Purchase Order 161427-OS for DXP Enterprises, Inc. to rebuild the PEPS Pump #3 based on their previous inspection report that identified major part replacements to restore pump performance.

 

TIMING CONCERNS

 

Delays in approving this work may result in treatment plant secondary treatment capacity limitations for additional wet weather (high flow) seasons.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If PEPS Pump No. 3 cannot operate per design, primary effluent treatment will potentially be impacted at Plant No. 1 during wet weather events.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

DXP Enterprises, Inc. is the Original Equipment Manufacturer and is the authorized service provider within OC San’s geographical region.  PEPS Pump No. 3 was removed and shipped to the service provider for teardown, inspection, and assessment.  Based on the assessment, approval of additional funds are required to repair and refurbish the pump.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance.  This recommendation will be funded under the Plant No. 1 and Plant No. 2 Maintenance Department, Budget Update 2023-2024, Page 39.  The available funding is sufficient for this action.

 

Date of Approval

Contract Amount

Contingency

03/27/2024

$322,061

$32,206 (10%)

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

N/A

 

RZ:ls