File #: 2023-3037    Version: 1 Name:
Type: Consent Status: Passed
File created: 6/8/2023 In control: OPERATIONS COMMITTEE
On agenda: 6/28/2023 Final action: 6/28/2023
Title: LIQUID OXYGEN (LOX) PURCHASE, SPECIFICATION NO. C-2023-1398BD
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report, 2. Chemical Supplier Agreement C-2023-1398BD
Related files: 2023-3001

FROM:                     Robert Thompson, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance 

 

SUBJECT:

 

title

LIQUID OXYGEN (LOX) PURCHASE, SPECIFICATION NO. C-2023-1398BD

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Approve a Chemical Supplier Agreement to Airgas USA, LLC for the purchase of liquid oxygen, Specification No. C-2023-1398BD for the period beginning August 21, 2023 through August 20, 2024, for a unit price of $0.53 per centum cubic feet (ccf) delivered, plus applicable sales tax, for a total estimated annual amount of $912,000; with four one-year renewal options; and

 

B.       Authorize unit price adjustment of up to 15% annually using mutually acceptable price indices for subsequent agreement renewal periods.

body

 

BACKGROUND

 

Orange County Sanitation District’s (OC San) Plant No. 2 facility requires liquid oxygen for the secondary treatment process.  OC San purchases liquid oxygen to reduce shipping volume and lower overall costs.  The liquid oxygen is vaporized on site and feeds as a gas to the activated sludge plant to remove biodegradable organic matter and suspended solids.

 

RELEVANT STANDARDS

 

                     Comply with environmental permit requirements

                     Maintain a culture of improving efficiency to reduce the cost to provide the current service level or standard

 

PROBLEM

 

The current liquid oxygen agreement will expire on August 20, 2023.

 

PROPOSED SOLUTION

 

Approve an agreement with Airgas USA, LLC for the purchase of liquid oxygen.

 

 

TIMING CONCERNS

 

OC San requires a new agreement to be in place before the existing agreement expires on August 20, 2023.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If the new vendor is not in place before the expiration of the existing contract, OC San would not be able to provide effective secondary treatment for Plant No. 2’s non-reclaimable flow.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

A Notice Inviting Bids was issued on March 24, 2023 via PlanetBids.  Bids were due on April 25, 2023.  OC San received three (3) bids valid for 180 calendar days from the bid opening date.  Linde Inc. has been determined as Non-Responsive due to taking exceptions to a number of items.  The following is a list of the firms that submitted a bid:

 

Company Name

Bid

Determination

AIRGAS USA, LLC

$0.53 Delivered Cost per CCF@STP = $912,000.00

Responsive

LINDE INC.

$0.98 Delivered Cost per CCF@STP = $1,680,000.00

Non-Responsive

WESTAIR GASES & EQUIPMENT

$1.00 Delivered Cost per CCF@STP = $1,728,000.00

Responsive

 

The bids which were evaluated in accordance with OC San’s Purchasing Ordinance.  Staff recommends approving an agreement to Airgas USA, LLC, the lowest responsive, responsible bidder.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance.  This item will be funded by the FY 2022-23 and 2023-24 approved budget for Plant No. 2 Operations Division.  (Line item: Repairs and Maintenance, Section 6, Page 88).

 

 

 

 

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Chemical Supplier Agreement