File #: 2021-1535    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 3/9/2021 In control: OPERATIONS COMMITTEE
On agenda: 10/6/2021 Final action: 10/6/2021
Title: SUNFLOWER PUMP REPLACEMENT AT PLANT NO. 1, PROJECT NO. FE19-04
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. FE19-04 Contract Agreement & Exhibit A (Schedule of Prices), 3. Presentation - FE19-04 Sunflower Pump Replacement
Related files: 2021-1895, 2024-3640

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

SUNFLOWER PUMP REPLACEMENT AT PLANT NO. 1, PROJECT NO. FE19-04

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Receive and file Bid Tabulation and Recommendation for Sunflower Pump Replacement at Plant No. 1, Project No. FE 19-04;

 

B.       Award a Construction Contract to GSE Construction Company Inc. for Sunflower Pump Replacement at Plant No. 1, Project No. FE19-04, for a total amount not to exceed $2,123,200; and

 

C.       Approve a contingency of $212,320 (10%).

 

bodyBACKGROUND

 

The Sunflower Pump Station transfers flows into the Headworks from the deepest of the trunk sewers feeding Plant No. 1.  The pump station uses two 40-million gallon per day screw pumps to lift flow from the Sunflower Trunk into Plant No. 1.  The screws for those pumps are approximately 32 feet long, have a 9-foot diameter, and are driven through a large gearbox to reduce the speed of the 150-horsepower motor down to 28 revolutions per minute.  These pumps are subject to erosion of the screws, corrosion from the sewer gas, and wear and tear on bearings submerged in wastewater.

 

The pump station is in the same area where the $222 million Headworks Rehabilitation at Plant No. 1, Project No. P1-105, is currently in construction.

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

                     Maintain a proactive asset management program

 

PROBLEM

 

Due to age, condition, and recent failures, both Sunflower pumps and pump components at the station are near the end of their useful life.  One of two pumps in particular needs immediate replacement, while the other pump can delay replacement for a few more years.

 

Replacement of the pumps must occur during the dry season because both pumps are needed during high flow events in the winter.  Only one pump can be replaced at a time, and replacement of one pump takes most of the six-month dry season.

 

PROPOSED SOLUTION

 

Award a construction contract for Sunflower Pump Replacement at Plant No. 1, Project No. FE19-04.  This project will replace one of the two pumps and associated equipment.  The second pump will be replaced later because replacing it on this contract would impact Headworks Rehabilitation at Plant No. 1, Project No. P1-105, which will be working in the same area.

 

TIMING CONCERNS

 

Awarding this contract now is important to allow the pump replacement to be completed before the 2023-2024 wet season.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

One of the pumps could fail during peak wet weather flows, which could result in a spill.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

The Orange County Sanitation District (OC San) advertised Project No. FE19-04 for bids on May 26, 2021, and eight on-line bids were received on July 15, 2021.  A summary of the bid opening follows:

 

Engineer’s Estimate

$2,700,000

 

 

Bidder

Amount of Bid

GSE Construction Company Inc.

$2,123,200

Tharsos Inc.

$2,151,000

PCL Construction, Inc.

$2,306,448

Kiewit Infrastructure West Co.

$2,365,000

Shimmick Construction Inc.

$2,559,000

Orion Construction Corporation

$2,647,000

Mehta Mechanical Company Inc.

$2,954,000

Abhe & Svoboda Inc.

$3,241,679

 

The bids were evaluated in accordance with OC San’s policies and procedures.  A notice was sent to all bidders on September 8, 2021, informing them of the intent of OC San staff to recommend award of the Construction Contract to GSE Construction Company Inc.

 

Staff recommends awarding a Construction Contract to the lowest responsive and responsible bidder, GSE Construction Company Inc., for a total amount not to exceed $2,123,200.

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301.  A Notice of Exemption will be filed with the OC Clerk-Recorder after OC San’s Board of Directors’ approval of the construction contract.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update, Fiscal Year 2021-2022, Appendix A, Page A-8, Small Construction Projects Program, Project No. M-FE) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Construction Contract

                     Presentation

 

SS:dm:gc