Legislation Details

File #: 2026-4918    Version: 1 Name:
Type: Non-Consent Status: Final
File created: 5/12/2026 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2026 Final action:
Title: ADMINISTRATIVE FACILITIES DEMOLITION, PROJECT NO. P1-141
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Construction Contract, 3. Presentation

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

ADMINISTRATIVE FACILITIES DEMOLITION, PROJECT NO. P1-141

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Receive and file  Bid Tabulation and Recommendation for Administrative Facilities Demolition, Project No. P1-141;

 

B.       Award a Construction Contract to Icon West, Inc. for Administrative Facilities Demolition, Project No. P1-141, for a total amount not to exceed $5,594,000; and

 

C.       Approve a contingency of $559,400 (10%). 

body

 

BACKGROUND

 

The Orange County Sanitation District’s (OC San) Administration and Human Resources Buildings at Plant No. 1 were vacated after the completion of the Headquarters Building.

 

RELEVANT STANDARDS

 

•                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

•                     Ensure the public’s money is wisely spent

•                     Sound engineering and accounting practices, complying with local, state, and federal laws

 

PROBLEM

 

The Administration and Human Resources Buildings are no longer needed and require demolition.

 

PROPOSED SOLUTION

 

Award a construction contract to demolish the vacant Administration and Human Resources Buildings.  The cleared site will be used for additional parking, public tour activities, and contractor staging while remaining available for future treatment facilities.

 

TIMING CONCERNS

 

Delaying the construction contract award would postpone demolition and the site’s availability for additional fleet parking and future contractor staging for Project No. P1-126, Primary Sedimentation Basins No. 3-5 Replacement at Plant No. 1.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Without awarding the construction contract, the existing Administration and Human Resources Buildings will remain in place, and ongoing maintenance costs for the vacant facilities will continue to accrue.  Consequently, the site will remain unavailable for short-term uses, including additional parking, public tours, and contractor staging, delaying its availability for future treatment process facilities.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

OC San advertised Project No. P1-141 for bids on August 19, 2026, and one sealed bid was received on September 29, 2026.  A summary of the bid opening follows:

 

Engineer’s Estimate

$11,380,000

Bidder

Amount of Bid

Icon West, Inc.

$5,594,000

 

OC San evaluated the bid in accordance with its policies and procedures.

 

The pre-bid conference and site visit were held on August 26, 2026, with 10 companies in attendance.  A pre-bid survey conducted on September 14, 2026, indicated that three contractors intended to bid, but only Icon West, Inc., submitted a bid.  One of the other interested contractors joined Icon West, Inc., as a subcontractor; the other reported that it began preparing its bid too late to obtain sufficient subcontractor quotations.

 

Icon West, Inc.’s bid was $5,786,000 (50.8%) below the Engineer’s Estimate.

 

The design consultant developed the Engineer's Estimate using conservative assumptions to account for uncertainties in building demolition, existing site conditions, construction methods, and market conditions.  OC San also obtained an independent estimate from its Supplemental Engineering Services consultant, which was generally consistent with the Engineer's Estimate.

 

Icon West, Inc., is also performing the nearby Support Buildings Seismic Improvements, Project No. P1-137.  Its presence at Plant No. 1 may provide efficiencies in mobilization, staffing, equipment use, and project management.

 

 

OC San staff reviewed the contractor’s detailed cost breakdown and clarifications, including trenching and shoring costs, and identified no significant omissions in the required scope of work.  Based on the overall evaluation, staff determined that Icon West, Inc., is a responsive and responsible bidder and that its bid is fair and reasonable.

 

CEQA

 

The Project is included in the Facilities Master Plan 2020 Program Environmental Impact Report (PEIR), State Clearinghouse Number 2019070998.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This recommendation would be funded under the Repairs and Maintenance line item for the Operations and Maintenance Department (Budget FY 2026-27 and 2027-28, Section 4, Page 3) and the available funding is sufficient for this action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

•                     Construction Contract

•                     Presentation

 

HO:lb