File #: 2022-2152    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/15/2022 In control: OPERATIONS COMMITTEE
On agenda: 3/16/2022 Final action: 3/16/2022
Title: REIMBURSEMENT AGREEMENT FOR ORANGE COUNTY SANITATION DISTRICT MANHOLE FRAME AND COVER ADJUSTMENTS ON EUCLID STREET IN THE CITY OF ANAHEIM
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. Draft Reimbursement Agreement

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

REIMBURSEMENT AGREEMENT FOR ORANGE COUNTY SANITATION DISTRICT MANHOLE FRAME AND COVER ADJUSTMENTS ON EUCLID STREET IN THE CITY OF ANAHEIM

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  

Approve and authorize the General Manager to execute a Reimbursement Agreement with the City of Anaheim for an amount not to exceed $180,000 for Orange County Sanitation District manhole frame and cover adjustments on Euclid Street in the City of Anaheim in a form approved by General Counsel.

body

 

BACKGROUND

 

The City of Anaheim (City) is working on a street rehabilitation project on Euclid Street from Broadway to the 91 Freeway.  This project generally consists of asphalt pavement resurfacing and associated improvements within the existing right-of-way.  Orange County Sanitation District (OC San) is responsible for adjusting the elevation of its infrastructure in the public right of way in order to maintain road safety and system function. 

 

The City intends to award the paving contract on March 01, 2022 which will include pricing to adjust OC San’s manholes effected by the contract.

 

RELEVANT STANDARDS

 

                     Protect OC San assets

                     Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities

 

PROBLEM

 

OC San owns 39 manholes within the limits of the City’s project.  These manholes will need to be adjusted to a final grade after the City resurfaces the pavement to maintain road safety and system function.

 

 

PROPOSED SOLUTION

 

Enter into a reimbursement agreement with the City for the City's awarded contractor to perform the manhole adjustment work.  OC San will provide the manhole frames and covers to the City, as well as inspection services to ensure the construction is in conformance with OC San standards.

 

TIMING CONCERNS

 

The Project is anticipated to start in April 2022 and be completed in August 2022.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If OC San does nothing, manhole frames and covers may be damaged, buried, or uneven with the finished road surface after the completion of the Project, posing a public-driving safety hazard.  If OC San decides to publicly bid and perform the work at a later date, it is likely to cost more and there will be additional street closures and impacts to the public.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

The reimbursement amount is based on the City's awarded unit price of $4,200 per manhole adjustment.  This equates to a total cost of $163,800.  An additional $16,200 was added to this amount to account for unknown conditions that may be discovered during paving and for change orders.  OC San will reimburse the City upon inspection and approval of manhole adjustment construction.

 

CEQA

 

CEQA compliance falls under the City’s project.

 

FINANCIAL CONSIDERATIONS

 

This recommendation would be funded under the Repairs and Maintenance line item for the Operations and Maintenance Department (Budget Update Fiscal Years FY 2021-2022, Page 45), and the available funding is sufficient for this action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 