Skip to main content
File #: 2023-3246    Version: 1 Name:
Type: Consent Status: Passed
File created: 9/25/2023 In control: OPERATIONS COMMITTEE
On agenda: 12/4/2024 Final action: 12/4/2024
Title: PLATFORM MODIFICATIONS FOR PROCESS AREAS AT PLANT NO. 1 AND NO. 2, PROJECT NO. FE22-01
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Draft Construction Contract Agreement - FE22-01
Related files: 2024-4004

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

PLATFORM MODIFICATIONS FOR PROCESS AREAS AT PLANT NO. 1 AND NO. 2, PROJECT NO. FE22-01

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Receive and file Bid Tabulation and Recommendation for Platform Modifications for Process Areas at Plant No. 1 and No. 2, Project No. FE22-01;

 

B.                          Award a Construction Contract Agreement to Tharsos, Inc., for Platform Modifications for Process Areas at Plant No. 1 and No. 2, Project No. FE22-01, for a total amount not to exceed $494,494; and

 

C.       Approve a contingency of $74,174 (15%).

body

 

BACKGROUND

 

The Orange County Sanitation District (OC San) operates facilities that manage wastewater, biosolids, and screened waste.  These include the Steve Anderson Lift Station (SALS), the Solids Storage Facility at Plant No. 1, and the Screenings Loading Building at Plant No. 2.  These facilities rely on pumps to move wastewater and solids through the treatment process.  To ensure they function reliably, regular inspections and routine maintenance are necessary.

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

                     Commitment to safety & reducing risk in all operations

 

PROBLEM

 

Several safety concerns are making it difficult for staff to perform routine maintenance effectively and safely.  In the SALS, the pumps are positioned on concrete pedestals that are difficult to access.  These pedestals lack guardrails and tie-off points, which poses a fall hazard for staff performing maintenance.  In the Solids Storage Building, a cake pump is located directly under the motor and gearbox, blocking access to the area, and preventing staff from using step ladders to reach the equipment safely.  In the Screenings Loading Building, staff are forced to step on the handrail rungs to reach and clear the screenings conveyor belt.  This unsafe practice complicates maintenance and increases the risk of injury.

 

PROPOSED SOLUTION

 

Award a Construction Contract Agreement for Platform Modifications for Process Areas at Plant No. 1 and No. 2, Project No. FE22-01.  This project will improve maintenance access at SALS, the Solids Storage Building, and the Screenings Loading Building and install an overhead monorail beam in the Screenings Loading Building.

 

Due to the relatively small construction value, staff recommends a contingency of 15%.  If an unknown condition is encountered and there is insufficient contingency, contract completion could be significantly delayed and expose OC San to extended overhead costs by the contractor.

 

TIMING CONCERNS

 

The timely approval of this contract will help ensure hard to reach areas for inspection and maintenance will be improved as soon as possible to maintain a safe work environment.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

If no action is taken, operations and maintenance staff will continue maintaining the existing equipment with unsafe, restricted access.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

 

ADDITIONAL INFORMATION

 

OC San advertised Project No. FE22-01 for bids on June 19, 2024, and eight sealed bids were received on September 10, 2024.  A summary of the bid opening follows:

 

Engineer’s Estimate

$ 724,000

Bidder

Amount of Bid

Tharsos, Inc.

$494,494

Vicon Enterprise, Inc.

$790,000

Filanc

$816,960

Marjani Builders, Inc.

$822,000

Innovative Construction Solutions

$845,000

Mehta Mechanical Co., Inc. DBA MMC Inc.

$854,000

United Contractors, Inc.

$988,130.50

Minako America Corporation, dba Minaco Construction

$1,477,300

The bids were evaluated in accordance with the OC San’s policies and procedures.  A notice was sent to all bidders on November 21, 2024, informing them of the intent of OC San’s staff to recommend award of the Construction Contract Agreement to Tharsos, Inc.

 

Staff recommends awarding a Construction Contract Agreement to Tharsos, Inc., the lowest responsive and responsible bidder.

 

CEQA

 

The project is exempt from CEQA and a Notice of Exemption will be filed with the OC Clerk-Recorder and State Clearing House after the OC San's Board of Directors approval of the Construction Contract Agreement.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget FY 2024-25 and 2025-26, Section 8, Page 49, Small Construction Projects Program, Project No. M-FE) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Draft Construction Contract Agreement

 

 

RD:lb