File #: 2023-3069    Version: 1 Name:
Type: Consent Status: Passed
File created: 6/20/2023 In control: OPERATIONS COMMITTEE
On agenda: 7/5/2023 Final action: 7/5/2023
Title: HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A
Sponsors: Mike Dorman
Attachments: 1. Agenda Report
Related files: 2021-1527, 2021-1640, 2023-3092, 2023-3264

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering

 

SUBJECT:

 

title

HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

Approve a contingency increase of $98,000 (2%) to the Professional Construction Services Agreement with HDR Engineering, Inc. for Headquarters Complex at Plant No. 1, Project No. P1-128A, for a total contingency of $588,000 (12%) and a total amount not to exceed $5,488,000.

body

 

BACKGROUND

 

Orange County Sanitation District (OC San) is constructing a new Headquarters Complex under Project No. P1-128A.  The new Headquarters Complex will house administrative, technical, and engineering staff.  Construction started in July 2021 and is scheduled for completion in early 2024.  HDR Engineering, Inc. is currently under contract to provide professional construction services for the new Headquarters Complex.

 

RELEVANT STANDARDS

 

                     Ensure the public’s money is wisely spent

                     Provide a safe and collegial workspace

 

PROBLEM

 

The level of effort needed to provide adequate construction support services is expected to exceed the assumptions the Professional Construction Services Agreement was based on.

 

PROPOSED SOLUTION

 

Approve a contingency increase to the Professional Construction Services Agreement.  The existing project budget is sufficient to cover the requested increase in contingency therefore no increase to the project budget is required.

 

 

 

TIMING CONCERNS

 

The construction schedule must be maintained, or staff occupation of the new building will be delayed.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

The Professional Construction Services Agreement “not to exceed” fee will not be sufficient to appropriately provide the remaining professional construction service.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

May 2021 - Approved a Professional Construction Services Agreement with HDR Engineering, Inc. to provide construction support services for Headquarters Complex at Plant No. 1, Contract No. P1-128A, for an amount not to exceed $4,900,000; and approved a contingency of $490,000 (10%).

 

ADDITIONAL INFORMATION

 

The level of effort assumed in the Professional Construction Services Agreement included assumptions such as the number of resubmittals, requests for information, and design changes due to unexpected field conditions.  These assumptions were based on the best available information and experience with past projects.  The level of effort to complete the job, however, is projected to exceed what was anticipated due to more submittals than anticipated and the rework of the fixture, furniture, and equipment procurement with another dealer.

 

CEQA

 

The Headquarters Complex project is included in the Addendum to the City of Fountain Valley “Fountain Valley Crossings Specific Plan” Program Environmental Impact Report, State Clearinghouse No. 2015101042.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update, Fiscal Year 2023-2024, Appendix A, Page 8, Headquarters Complex, Project No. P1-128) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

N/A

 

AB:tk