FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering
SUBJECT:
title
TRUCK LOADING HYDRAULIC POWER UNIT UPGRADES AT PLANT NO. 2, PROJECT NO. FE26-03
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION: Recommend to the Board of Directors to:
A. Approve a Sole Source Purchase Order to Putzmeister America, Inc., for the purchase of four Model HA 55 CI hydraulic power units, two local control panels, and 12 Bosch Rexroth Hydromotors for auger screws for the Truck Loading Hydraulic Power Unit Upgrades at Plant No. 2, Project No. FE26-03 for a total amount not to exceed $1,019,330, including engineering and applicable sales tax and freight; and
B. Approve a contingency of $101,933 (10%).
body
BACKGROUND
The Orange County Sanitation District (OC San) operates the Truck Loading Facility at Plant No. 2 to load biosolid trucks. The facility consists of two truck loading bays, Bay A and Bay B. Each bay has six augers and one sliding frame. The augers and sliding frames are controlled by hydraulic power units and local control panels.
The existing Solid Storage and Truck Loading Facility was constructed in 2000. In 2019, OC San began using centrifuges to remove more water from biosolids before truck loading. The solids content increased from 18-20% to 25-30%.
The existing truck loading system consists of custom-designed Putzmeister equipment. Putzmeister is on the Board-approved Original Equipment Manufacturer (OEM) Sole Source List, approved in May 2020.
RELEVANT STANDARDS
• 24/7/365 treatment plant reliability
• Protect OC San assets
PROBLEM
The hydraulic power units have exceeded their useful life and replacement parts for the local control panels are becoming difficult to obtain. The existing auger motors need to be increased in size to properly accommodate thicker biosolids to prevent high-torque alarms.
PROPOSED SOLUTION
Approve the sole source purchase of replacement hydraulic power units, local control panels, and auger drive motors for the Plant No. 2 Truck Loading Facility. Purchasing all components from Putzmeister provides a single supplier responsible for equipment compatibility and integrated system performance. A sole source purchase is required to maintain compatibility with the existing system. Installation will be performed under a separate contract.
TIMING CONCERNS
Delaying approval would postpone ordering equipment with long procurement lead times and extend reliance on aging equipment. The replacement work must be performed prior to Project No. P2-140, Truck Loading Bay Odor Control Improvements at Plant No. 2, which includes work in the truck loading bays and is scheduled to be in construction from December 2028 to December 2030. Due to the condition of the existing equipment, replacement cannot wait until Project No. P2-140 is complete.
RAMIFICATIONS OF NOT TAKING ACTION
Without this purchase, OC San would continue using equipment at increased risk of failure. An equipment failure could disrupt truck loading and off-site biosolids hauling and require costly emergency replacement.
PRIOR COMMITTEE/BOARD ACTIONS
N/A
ADDITIONAL INFORMATION
N/A
CEQA
N/A
FINANCIAL CONSIDERATIONS
This request complies with the authority levels of OC San’s Purchasing Ordinance. This item has been budgeted (Budget FY 2026-27 and FY 2027-28, Section 8, Page 47, Small Construction Projects Program, Project No. M-FE_FY26), and the budget is sufficient for the recommended action.
ATTACHMENT
The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:
• Presentation
SG:lb