File #: 2021-1732    Version: 1 Name:
Type: Consent Status: Passed
File created: 6/17/2021 In control: OPERATIONS COMMITTEE
On agenda: 10/6/2021 Final action: 10/6/2021
Title: TRUCK LOADING BASEMENT DRAIN MODIFICATIONS AT PLANT NO. 1, PROJECT NO. FE18-16
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. FE18-16 Contract Agreement & Exhibit A (Schedule of Prices)

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

TRUCK LOADING BASEMENT DRAIN MODIFICATIONS AT PLANT NO. 1, PROJECT NO. FE18-16

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Receive and file Bid Tabulation and Recommendation for Truck Loading Basement Drain Modifications at Plant No. 1, Project No. FE18-16;

 

B.       Award a Construction Contract to Metha Mechanical Company, Inc. for Truck Loading Basement Drain Modifications at Plant No. 1, Project No. FE18-16, for an amount not to exceed $162,500; and

 

C.       Approve a contingency of $16,250 (10%).

 

body

BACKGROUND

 

Biosolids are dewatered solids produced as a byproduct of wastewater treatment.  The Orange County Sanitation District (OC San) recently completed a project to add centrifuges to reduce the water content of biosolids, thereby saving offsite hauling costs.  The dewatered biosolids are routed through an existing truck loading station.  Any biosolids that are deposited on the floor during maintenance of the truck loading station are returned to the treatment system through floor drains.

 

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

                     Maintain a proactive asset management program

 

 

PROBLEM

 

Performing maintenance on the truck loading facility results in biosolids falling on the floor.  The existing drains were not designed for the thicker biosolids produced by the centrifuges.  In addition, the new transfer pumps installed with the centrifuges are larger than the original pumps, so the pump bases have unavoidably blocked some of the drains.  As a result, removing the resulting material can often take longer than the actual maintenance activity.

 

PROPOSED SOLUTION

 

Award a Construction Contract for Truck Loading Basement Drain Modifications at Plant No, 1, Project No. FE18-16.  This project enlarges the opening of existing floor drains, replaces the existing sump pumps with two new submersible chopper pumps, modifies the existing sump pit, and cores new drains into the concrete pads of all four cake transfer pumps to improve drainage at the truck loading basement.

 

TIMING CONCERNS

 

If this project is delayed, maintenance in the truck loading basement will continue to require an unreasonably large effort to clean the facility after the work is performed.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Maintenance in the truck loading basement will continue to require an unreasonably large effort to clean the facility after the work is performed.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

OC San advertised Project No. FE18-16 for bids on June 29, 2021, and six bids were received on August 8, 2021.  A summary of the bid opening follows:

 

Engineer’s Estimate                                                                 $169,000

 

Bidder                                                                                        Amount of Bid

Metha Mechanical Company, Inc.                                                                                    $162,500

Tharsos, Inc.                                                                               $189,400

W.A. Rasic Construction Company, Inc.                                     $194,400

J.R. Filanc Construction Co., Inc.                                                 $198,500

Cora Constructors, Inc.                                                                $263,500

Abhe & Svoboda, Inc.                                                                  $284,648

 

The bids were evaluated in accordance with OC San’s policies and procedures.  A notice was sent to all bidders on August 23, 2021, informing them of the intent of OC San to recommend award of the construction contract to Metha Mechanical Company, Inc.

 

Staff recommends awarding a Construction Contract to the lowest responsive and responsible bidder, Metha Mechanical Company, Inc., for a total amount not to exceed $162,500.

 

CEQA

 

The project is exempt from CEQA under the categorical exemption set forth in CEQA Guidelines Class 1 Section 15301.  A Notice of Exemption was filed on July 28, 2020.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget Update, Fiscal Year 2021-2022, Appendix A, Page A-8, Small Construction Projects Program, Project No. M-FE) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Construction Contract

 

DR:dm:gc