Legislation Details

File #: 2026-4925    Version: 1 Name:
Type: Non-Consent Status: Final
File created: 5/14/2026 In control: OPERATIONS COMMITTEE
On agenda: 6/3/2026 Final action:
Title: GISLER-RED HILL INTERCEPTOR AND BAKER FORCE MAIN REHABILITATION, PROJECT NO. 7-65
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Presentation - 7-65 PCSA Contingency
Related files: 2023-2980

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

GISLER-RED HILL INTERCEPTOR AND BAKER FORCE MAIN REHABILITATION, PROJECT NO. 7-65

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

Approve a Contingency Increase of $ 296,538 (30%) to the existing Professional Construction Services Agreement with CDM Smith, Inc. to provide construction support services for Gisler-Red Hill Interceptor and Baker Force Main Rehabilitation, Project No. 7-65, for a new total contingency amount of $395,384 (40%).

body

 

BACKGROUND

 

This project is rehabilitating approximately 8,600 linear feet of the Gisler-Red Hill Interceptor and approximately 12,000 linear feet of the Baker force mains.  The project also includes replacing corroded and damaged piping, valves, and valve vaults at the Main Street Pump Station.

 

CDM Smith, Inc. is currently under contract to provide professional construction services to support the construction of Project No. 7-65.

 

RELEVANT STANDARDS

 

                     Ensure the public’s money is wisely spent

                     Achieve less than 2.1 sewer spills per 100 miles

 

PROBLEM

 

The original Professional Construction Services Agreement (PCSA) assumed a certain level of effort based on the estimated number of submittals and requests for information (RFIs).  These estimates were developed using the best available information and experience from similar projects.

 

Due to the complexity of the project, the actual level of effort has been significantly higher than anticipated.  The consultant has experienced higher workloads than originally anticipated, supporting more than double the estimated number of RFIs and Submittals.  In addition, construction delays have extended the construction schedule by approximately 14 months.

As a result, the consultant has exhausted the current contract budget and requires additional funding to continue providing construction support services through project completion.

 

PROPOSED SOLUTION

 

Approve a Contingency Increase to allow the authorization of a PCSA amendment to allow the consultant to continue providing construction support services through project completion.

 

TIMING CONCERNS

 

If this amendment is not approved, the consultant will exhaust the remaining contract budget before construction is complete.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

The remaining PCSA contract budget will not be sufficient for the consultant to provide the construction support services needed through project completion.  OC San would need to use internal staff resources or procure additional support services to complete the project.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

May 2023 - Approved a Professional Construction Services Agreement with CDM Smith Inc. to provide construction support services for Gisler-Red Hill Interceptor and Baker Force Main Rehabilitation, Project No. 7-65, for a total amount not to exceed $988,460; and approved a contingency of $98,846 (10%).

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301.  A Notice of Exemption has been filed with the OC Clerk-Recorder.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.   This item has been budgeted (Budget Update FY 2025-26, Page A-5, Gisler-Red Hill Interceptor & Baker Force Main Rehabilitation Project No. 7-65) and the budget is sufficient for the recommended action.

 