File #: 2022-2623    Version: 1 Name:
Type: Consent Status: Passed
File created: 11/3/2022 In control: OPERATIONS COMMITTEE
On agenda: 11/16/2022 Final action: 11/16/2022
Title: CONSTRUCTION OUTREACH SUPPORT SERVICES
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. Professional Consultant Services Agreement
Related files: 2022-2565

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

CONSTRUCTION OUTREACH SUPPORT SERVICES

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

 

A.       Approve a Professional Consultant Services Agreement with Katz & Associates, Inc. to provide Construction Outreach Support Services, Specification No. CS-2022-1329BD, for a total amount not to exceed $450,000 for a three-year term;

 

B.       Approve a contingency of $45,000 (10%) for the first three-year term;

 

C.       Approve two (2) one-year optional renewals for an annual amount not to exceed $150,000 per year; and

 

D.       Approve an annual contingency of $15,000 (10%) for each optional year.

body

 

BACKGROUND

 

Orange County Sanitation District (OC San) manages a $3 billion dollar Capital Improvement Program (CIP) with more than 90 projects occurring simultaneously at Plant No. 1, Plant No. 2, and throughout Orange County.  To support the CIP, OC San has an extensive Construction Outreach Program as part of the Organizational Outreach and Advocacy goal within the Board adopted Strategic Plan.  This program aims to keep the community and the various stakeholders informed of the CIP project activities.

 

Through the outreach program, relationships are established with the cities and ratepayers that are often initially unfamiliar with the agency and the services OC San provides.  The outreach program introduces OC San, the need for the projects, and the benefits to the community which minimizes public complaints.  Establishing contact and communication with the community early on helps build trust and allows for a smoother project start up and project completion, while also minimizing the workload and complaints from going directly to the cities.

 

RELEVANT STANDARDS

 

                     Build brand, trust, and support with policy makers and community leaders

                     Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities

                     Maintain influential legislative advocacy and a public outreach program

                     Make it easy for people to understand OC San’s roles and value to the community

 

PROBLEM

 

Historically, the outreach program is managed internally with the support of sub-consultants as part of the design or construction contract.  With the number of projects and potential overlap, a design consultant by project based approach can become complicated and cause confusion.  In addition, without a centralized program, significant internal resources would be required and would cause a significant strain on staff to provide the proper outreach coordination while also supporting the other public affairs programs within the agency.

 

PROPOSED SOLUTION

 

Due to the large number of projects occurring simultaneously throughout various cities, OC San is proposing to reallocate the individual construction outreach budget within each of the individual projects to one centralized program to effectively maintain a smooth, efficient, and consistent program.  Staff recommends approving an agreement to help support the outreach efforts for the CIP.  Over the next few years, the CIP will have almost 20 projects with a combined construction cost of $730 million in design and construction that need outreach support.  The selected team will help support the outreach for these projects.

 

TIMING CONCERNS

 

Large scale projects within the collection system are nearing the construction phase.  Having Katz & Associates onboard prior to construction start will allow individual outreach plans to be developed and implemented to minimize public concerns.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Without supplementing the outreach program team, OC San will not have the necessary resources on hand to properly develop, implement, and support the various CIP projects to our current level of service.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

Consultant Selection:

 

OC San requested and advertised for proposals for Construction Outreach Support Services on July 7, 2022.  The following evaluation criteria were described in the Request for Proposals (RFP) and used to determine the most qualified Consultant.

 

CRITERION

WEIGHT

Work Plan

25%

Qualifications & Experience of Firm

20%

Proposed Staffing & Project Organization

20%

Presentation/Interview

15%

Cost

20%

 

Three proposals were received on August 12, 2022 and evaluated in accordance with the evaluation process set forth in OC San’s Purchasing Ordinance by a pre-selected Evaluation Team consisting of the following OC San staff:  Administration Manager, Engineering Supervisor, Principal Public Affairs Specialist, Senior Engineer, and Principal Staff Analyst.  The evaluation team also included one non-voting representative from the Purchasing Division.  The Evaluation Team scored the proposals on the established criteria as summarized in the table below.

 

Rank

Proposer

Criterion 1  (Max 25%)

Criterion 2 (Max 20%)

Criterion 3 (Max 20%)

Subtotal Score (Max 65%

1

Katz & Associates, Inc.

23%

18%

18%

59%

2

S. Groner Associates

19%

16%

13%

48%

3

Alliance Outreach

17%

15%

12%

44%

 

The two highest ranking firms, Katz & Associates, Inc. and S. Groner Associates, Inc., were selected for the presentation round.  Presentations took place on September 15, 2022.  Following the presentations, the evaluation team finalized scores based on both the proposals and presentations using the evaluation criteria and weighting listed above.

 

Rank

Proposer

Subtotal Score (Max 65%)

Presentation (Max 15%)

Total Score without cost (Max 80%)

1

Katz & Associates, Inc.

59%

14%

73%

2

S. Groner Associates

48%

8%

56%

 

All proposals were accompanied by a sealed cost proposal.  Due to the natural break in the scoring after the interviews, only the cost proposal for the highest ranked firm was opened and negotiated.

 

Rank

Proposer

 Subtotal Score (Max 65%)

Presentation (Max 15%)

Cost    (Max 20%)

Total Weighted Score      (Max 100%)

1

Katz & Associates, Inc.

59%

14%

20%

93%

 

 

 

 

 

Cost Information for Opened Proposals:

 

Rank

Proposer

Cost

1

Katz & Associates, Inc.

$450,000

 

Staff is recommending approval of a 10% contingency that may be used for increased support to accommodate developments and implementation of the CIP.

 

Based on these results, staff recommends approving a Professional Consultant Services Agreement to Katz & Associates, Inc.  The term of this Agreement will begin upon effective date of the Notice to Proceed.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted as a part of the CIP.

 

Date of Approval

Contract Amount

Contingency

11/16/2022

$450,000

$45,000 (10%)

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Professional Consultant Services Agreement