File #: 2024-3668    Version: 1 Name:
Type: Consent Status: Passed
File created: 6/14/2024 In control: OPERATIONS COMMITTEE
On agenda: 7/10/2024 Final action: 7/10/2024
Title: HVAC REPLACEMENTS AT PLANT NOS. 1 AND 2, PROJECT NO. FE23-06
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Supplemental Attachment - FE23-06
Related files: 2024-3714

FROM:                     Robert Thompson, General Manager

                     Originator: Mike Dorman, Director of Engineering 

 

SUBJECT:

 

title

HVAC REPLACEMENTS AT PLANT NOS. 1 AND 2, PROJECT NO. FE23-06

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

A.       Approve a Purchase Order Contract to ACCO Engineered Systems, Inc. for the HVAC Replacements at Plant Nos. 1 and 2, Project No. FE23-06, utilizing the Omnia Cooperative Purchasing Agreement, Contract Number #02-73, for a total amount not to exceed $1,698,204; and

 

B.       Approve a contingency of $169,820 (10%).

body

 

BACKGROUND

 

The electrical rooms at Orange County Sanitation District (OC San) Plant No. 1 Steve Anderson Lift Station, Plant No. 1 City Water Pump Station, Plant No. 2 Gas Compressor electrical building, Plant No. 2 East and West RAS Pump Stations, and Plant No. 1 Primary Clarifiers use HVAC units to clean, cool, and dry air to protect the electrical equipment and keep them from overheating.

 

RELEVANT STANDARDS

 

                     Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder

                     24/7/365 treatment plant reliability

 

PROBLEM

 

The HVAC outdoor air coils and metallic components are showing extreme wear and are experiencing failure.  The maintenance staff has repaired the units several times; however, the units are at a point where further repair or maintenance will not offer acceptable reliability.  In addition, the HVAC equipment on the buildings have passed their useful life expectancy and can no longer be maintained reliably.

 

 

 

PROPOSED SOLUTION

 

Approve a Purchase Order Contract for HVAC Replacements at Plant Nos. 1 and 2, Project No. FE23-06.  This project will replace in kind the 15 HVAC units at the various buildings.

 

TIMING CONCERNS

 

This purchase order contract designs, replaces, and commissions new HVAC equipment in the most timely and efficient manner.  Delaying this action means OC San will be vulnerable to the potential shutdown of electrical equipment within the buildings due to overheating or contamination.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Not replacing these units will increase the risk of overheating and the eventual shutdown or failure of critical electrical equipment in the buildings, which would cause Treatment Plant disruptions.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

OC San is utilizing a cooperative agreement through Omnia Partners, formerly U.S. Communities, which is the largest cooperative purchasing organization for public sector procurement.  This agreement was awarded using a competitive bid process similar to OC San’s and has been vetted by OC San’s Purchasing Division.  The collective buying power of the unified purchasing cooperatives typically deliver value and savings for public agencies nationwide.

 

ACCO Engineered Systems, Inc. was selected to propose on this cooperative agreement because they can provide equipment that meets the needs of OC San expeditiously.  The total amount of bid under this cooperative agreement is $1,698,204.

 

Staff evaluated the proposal in accordance with OC San policies and procedures and based on these results, recommends approving a Purchase Order Contract to ACCO Engineered Systems, Inc. to replace the following equipment:

 

Location

HVAC Quantity and Size

SALS Building Roof and Electrical Room

Two (2) 8-ton Fan Units                            Two (2) 8-ton Condenser Units

City Water Pump Station

Two (2) 3-ton HVAC units

Gas Compressor Electrical Building

One (1) 4-ton HVAC unit

East and West RAS Pump Stations

Two (2) 8.5-ton Packaged HVAC units     Two (2) 5-ton Heat Pumps

Plant 1 Rectangular Primary Clarifiers

Two (2) 10-ton Air Handler Units            Two (2) 10-ton Condenser Units

 

CEQA

 

The project is exempt from CEQA under the Class 1 categorical exemptions set forth in California Code of Regulations Section 15301.  A Notice of Exemption will be filed with the OC Clerk-Recorder after OC San Board of Directors approval.

 

FINANCIAL CONSIDERATIONS

 

This request complies with the authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (Budget FY 2024-25 and 2025-26, Section 8, Page 49, Small Construction Projects Program, Project No. M-FE) and the budget is sufficient for the recommended action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Supplemental Attachment - FE23-06 Photos

 

 

 

SS:lb