Legislation Details

File #: 2026-5201    Version: 1 Name:
Type: Consent Status: Final
File created: 11/12/2026 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2026 Final action:
Title: PLANT NO. 1 REPLACEMENT GEARBOX FOR TRICKLING FILTER CLARIFIER 1
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report
Related files: 2025-4115

FROM:                     Robert Thompson, General Manager

                     Originator: Riaz Moinuddin, Director of Operations & Maintenance 

 

SUBJECT:

 

title

PLANT NO. 1 REPLACEMENT GEARBOX FOR TRICKLING FILTER CLARIFIER 1

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

A.       Approve a Sole Source Purchase Order to Ovivo USA, LLC, for the procurement of one Ovivo C80 clarifier drive unit for Trickling Filter Clarifier 1, for a total amount not to exceed $159,653, plus applicable sales tax; and

 

B.       Approve a contingency of $15,965 (10%).

body

 

BACKGROUND

 

Orange County Sanitation District (OC San) Plant No. 1 operates two 145-foot-diameter Trickling Filter Clarifiers.  Trickling filter clarifiers are sedimentation tanks downstream of a trickling filter to remove settleable solids and sloughed biological growth.  These two clarifiers provide secondary treatment for approximately 30 million gallons per day (MGD) of wastewater.  Secondary effluent is conveyed to the Groundwater Replenishment System or discharged through the ocean outfall.  Reliable clarifier operation is essential to maintain treatment capacity and regulatory compliance.

 

RELEVANT STANDARDS

 

•                     24/7/365 Treatment plant reliability

•                     Protect OC San Assets

•                     Maintain a proactive asset management program

 

PROBLEM

 

A recent inspection identified a leak in Trickling Filter Clarifier 1 C80 drive unit (a high-torque motorized gearbox assembly that slowly rotates sludge collector rake arms to sweep settled biomass and sloughed biofilm for removal) requiring a complete rebuild or replacement. Failure of the drive unit could render the clarifier inoperable, reducing secondary treatment capacity and affecting process reliability.

 

 

PROPOSED SOLUTION

 

Procure a new C80 clarifier drive unit for Plant No. 1’s Trickling Filter Clarifier from Ovivo USA, LLC to maintain asset reliability and minimize process downtime.

 

TIMING CONCERNS

 

The replacement drive unit has a 22-week lead time.  Delaying procurement increases the risk of extended clarifier downtime and reduced treatment capacity should the existing drive fail.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Failure of the existing drive unit could result in prolonged clarifier downtime, reduced treatment capacity, and increased risk of regulatory noncompliance.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

February 2025 - Approved Ovivo, as an Original Equipment Manufacturer (OEM) sole-source supplier for Ovivo Parts and Equipment Used in Water and Wastewater Treatment Processes.

 

ADDITIONAL INFORMATION

 

N/A

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of OC San’s Purchasing Ordinance.  This item has been budgeted (FY 2025-26, Pages A-15 and A-18, Emergency Capital Critical Spare), and the budget is sufficient for this action.

 

Date of Approval

Contract Amount

Contingency

12/2/2026

$159,653

$15,965

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 