FROM:	James D. Herberg, General Manager
	Originator: Kathy Millea, Director of Engineering  
SUBJECT:
title
REDHILL RELIEF SEWER RELOCATION AT STATE ROUTE 55, PROJECT NO. FE18-13
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION:  Recommend to the Board of Directors to:
A.       Receive and file Bid Tabulation and Recommendation for Redhill Relief Sewer Relocation at State Route 55, Project No. FE18-13; 
B.       Award a Construction Contract to SRK Engineering, Inc. for Redhill Relief Sewer Relocation at State Route 55, Project No. FE18-13 for an amount not to exceed $2,213,000; and
C.       Approve a contingency of $331,950 (15%). 
body
BACKGROUND 
The Orange County Transportation Authority (OCTA) is implementing the State Route 55 (SR-55) Improvement Project to widen SR-55 between Interstate 5 and Interstate 405.  The Orange County Sanitation District (OC San) owns a sewer running under SR-55 immediately south of Warner Avenue in the City of Santa Ana. 
RELEVANT STANDARDS
* Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder
* Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities
* Protect OC San assets
PROBLEM 
The SR-55 Improvement Project will widen the freeway over an existing OC San sewer.  To protect the sewer, OC San must encase the sewer in the newly widened right-of-way and move an interfering manhole outside the freeway limits.
PROPOSED SOLUTION
Award a contract for Redhill Relief Sewer Relocation at State Route 55 to SRK Engineering, Inc.  This project will extend a protective casing for the portions of the sewer to remain under the widened freeway and relocate a manhole out of the widened right-of-way.  Moving the manhole requires a sewer realignment and the addition of three new manholes to avoid a retaining wall along Warner Avenue.
OCTA has agreed to compensate OC San for t...