FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance
SUBJECT:
title
MP2-0010 PRIMARY EFFLUENT PUMP STATION PUMP NOS. 1, 2, AND 3 OVERHAUL AT PLANT NO. 2
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION:
A. Approve a Sole Source Services Contract for MP2-0010 Primary Effluent Pump Station (PEPS) Pump Nos. 1, 2, and 3 Overhaul at Plant No. 2 to Vaughan's Industrial Repair Co., Inc. to rebuild three (3) Fairbanks Morse vertical pumps, for a total amount not to exceed $619,774; and
B. Approve a contingency of $61,977 (10%).
body
BACKGROUND
The Orange County Sanitation District (OC San) Plant No. 2 PEPS conveys non-reclaimable primary-treated wastewater to the Activated Sludge (AS) process for secondary treatment prior to discharge through the ocean outfall. The PEPS Pump Station is comprised of four pumps that were originally installed over 40 years ago by Project P1-16 in 1981.
RELEVANT STANDARDS
* 24/7/365 treatment plant reliability
* Comply with environmental permit requirements
* Maintain a proactive asset management program
* Operate and maintain facilities to minimize impacts on surrounding communities, including odor, noise, and lighting
PROBLEM
A recent rebuild of the PEPS Pump No. 4 at OC San Plant No. 2 found degradation and damage that needed repairs on the discharge elbow, pump impeller, and suction bell. PEPS Pump Nos. 1, 2, and 3 have been in service for the same amount of time and require removal and repair before any major parts are damaged beyond repair.
PROPOSED SOLUTION
Approve a Sole Source Service Contract with a fixed 3-year contract, one pump per year, to Vaughan's Industrial Repair Co., Inc. to rebuild the Fairbanks Morse PEPS Pumps. The pumps need to be overhauled to give units a longer life cycle and before damaged parts become obsolete.
TIMING CONCERNS
The existing three PEPS Pumps are 40 years old and are showing signs of degradat...