FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering
SUBJECT:
title
DEEP WELL INJECTION FACILITY, PROJECT NO. J-143
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION: Recommend to the Board of Directors to:
A. Approve a Progressive Design-Build Contract with Filanc to provide Phase 1 engineering and preconstruction services, for the Deep Well Injection Facility, Project No. J-143, for a total amount not to exceed $13,477,557; and
B. Approve a contingency of $1,347,756 (10%).
body
BACKGROUND
The Orange County Sanitation District (OC San) treats wastewater at Plant Nos. 1 and 2 and generates biosolids that are transported off site for management and beneficial use. OC San has studied deep well injection as a potential long-term option for managing these solids.
Deep well injection would place processed solids into suitable deep underground formations. Initial surface facilities would serve Plant No. 1. Future facilities at Plant No. 1 could consist of a receiving station for Plant No. 2 biosolids, an interplant sludge line, or an alternate solution at Plant No. 2.
OC San selected Progressive Design-Build (PDB) delivery to develop design, cost, and risk information in stages before deciding whether to proceed with construction.
RELEVANT STANDARDS
Ensure the public's money is wisely spent
Comply with environmental permit requirements
Sound engineering and accounting practices, complying with local, state, and federal laws
Maintain a culture of improving efficiency to reduce the cost to provide the current service level or standard
PROBLEM
OC San currently relies on third-party contracts for long-distance hauling and off-site management of biosolids. This creates ongoing transportation costs and exposes OC San to changes in available off-site management options. OC San is also impacted by the changing biosolids market conditions.
OC San has determined that deep we...