File #: 2023-3122    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 7/18/2023 In control: STEERING COMMITTEE
On agenda: 7/26/2023 Final action: 7/26/2023
Title: HEADQUARTERS AUDIOVISUAL INTEGRATOR, CONTRACT NO. P1-128A-1 FOR HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO P1-128
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. P1-128-1 Contract
Related files: 2023-2953
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
HEADQUARTERS AUDIOVISUAL INTEGRATOR, CONTRACT NO. P1-128A-1 FOR HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO P1-128
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Receive and file Bid Tabulation and Recommendation for Headquarters Audiovisual Integrator, Contract No. P1-128A-1 for the Headquarters Complex at Plant No. 1, Project No. P1-128A;

B. Award a Construction Contract to EIDIM Group, Inc. dba EIDIM AV Technology for Headquarters Audiovisual Integrator, Contract No. P1-128A-1 for the Headquarters Complex at Plant No. 1, Project No. P1-128A for a total amount not to exceed $1,580,000; and

C. Approve a contingency of $158,000 (10%).
body

BACKGROUND

Orange County Sanitation District (OC San) is constructing a new Headquarters Complex under Project No. P1-128A. The new Headquarters Complex will require audiovisual equipment to function properly. The construction contract for the new building does not include the purchase, installation, and integration services of audiovisual equipment. The audiovisual equipment with known long lead times was procured separately from this contract to accommodate the possibility of delays.

RELEVANT STANDARDS

* Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder
* Ensure the public's money is wisely spent
* Provide a safe and collegial workspace


PROBLEM

The new Headquarters Complex requires an audiovisual network to be functional. While long lead-time audiovisual equipment and audiovisual network equipment have been approved and purchased, the remainder of the readily available equipment and installation services for the entire system has not been awarded.

PROPOSED SOLUTION

Award a construction contract for Headquarters Audiovisual Integrator, Contract No. P1-128A-1 for the Headqu...

Click here for full text