FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering
SUBJECT:
title
A-SIDE PRIMARY CLARIFIERS REPLACEMENT AT PLANT NO. 2, CONTRACT NO. P2-98A
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION: Recommend to the Board of Directors to:
A. Approve a project budget increase of $4,400,000 for A-Side Primary Clarifiers Replacement at Plant No. 2, Contract No. P2-98A as part of Primary Treatment Rehabilitation at Plant No. 2, Project No. P2-98, for a new total budget of $193,400,000; and
B. Approve a contingency increase of $1,680,000 (20%) for a new total contingency of $2,520,000 (30%) to the existing Professional Construction Services Agreement with Black & Veatch Corporation to provide construction support services for A-Side Primary Clarifiers Replacement at Plant No. 2, Contract No. P2-98A as part of Primary Treatment Rehabilitation at Plant No. 2, Project No. P2-98.
body
BACKGROUND
The primary treatment process removes solids from screened wastewater in large concrete structures called primary clarifiers. Orange County Sanitation District (OC San) has fourteen circular primary clarifiers at Plant No. 2, constructed between 1960 and 1985, including four A-Side clarifiers constructed between 1960 and 1963 that require complete replacement.
OC San executed the A-Side Primary Clarifiers Replacement Project, Contract No. P2-98A, to construct four primary clarifiers, an odor control and chemical facility, an electrical distribution center, and ancillary utilities and facilities. After the new facilities are completed, the four existing A-Side primary clarifiers, a power building, and an odor control facility will be demolished.
Construction began in July 2021 and is approximately 87% complete, with completion expected by late 2027.
RELEVANT STANDARDS
Ensure the public’s money is wisely spent
24/7/365 treatment plant reliability
PROBLEM
The existing Professional Construction Se...
Click here for full text