FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering
SUBJECT:
title
COLLECTIONS YARD RELOCATION AND WAREHOUSE DEMOLITION AT PLANT NO. 2, PROJECT NO. P2-127
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION: Recommend to the Board of Directors to:
A. Receive and file Bid Tabulation and Recommendation for Collections Yard Relocation and Warehouse Demolition at Plant No. 2, Project No. P2-127;
B. Receive and file Orange County Sanitation District's Notice of Intent to Award dated June 2, 2023;
C. Receive and file Award Protest from Fasone Construction, Inc. dated June 8, 2023 concerning award to Archico Design Build Inc.;
D. Receive and file the Award Protest Response letter from Archico Design Build Inc. dated June 14, 2023, responding to the award protest;
E. Receive and file Orange County Sanitation District's determination letter dated June 22, 2023 to Fasone Construction, Inc. responding to award protest;
F. Approve a project budget increase of $2,100,000 for Collections Yard Relocation and Warehouse Demolition at Plant No. 2, Project No. P2-127, for a new total project budget of $8,800,000;
G. Award a Construction Contract to Archico Design Build Inc. for Collections Yard Relocation and Warehouse Demolition at Plant No. 2, Project No. P2-127, for a total amount not to exceed $6,500,000; and
H. Approve a construction contingency of $650,000 (10%).
body
BACKGROUND
The Orange County Sanitation District (OC San) collections yard and warehouse at Plant No. 2 occupies the space needed for the construction of the new Temperature-Phased Anaerobic Digestion (TPAD) Digester Facility, Project No. P2-128. During the preliminary design phase of a project to replace the existing warehouse, it was determined that remote warehousing could be utilized in lieu of constructing a new building.
RELEVANT STANDARDS
* Comply with California Public Contract Code Se...