File #: 2026-4770    Version: Name:
Type: Consent Status: Passed
File created: 1/14/2026 In control: OPERATIONS COMMITTEE
On agenda: 2/4/2026 Final action: 2/4/2026
Title: ACTIVATED SLUDGE CLARIFIERS 11 AND 13 REHABILITATION AT PLANT NO. 1 (MP1-017), SPECIFICATION NO. S-2025-692BD
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report, 2. Service Contract, SP No, S-2025-692BD
Related files: 2026-4785
FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance

SUBJECT:

title
ACTIVATED SLUDGE CLARIFIERS 11 AND 13 REHABILITATION AT PLANT NO. 1 (MP1-017), SPECIFICATION NO. S-2025-692BD
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

A. Approve a Services Contract with Vicon Enterprise, Inc. for Activated Sludge Clarifiers 11 and 13 Rehabilitation at Plant No. 1(MP1-017), Specification No. S- 2025-692BD, for a total amount not to exceed $1,950,500; and

B. Approve a contingency of $195,050 (10%).
body

BACKGROUND

Orange County Sanitation District (OC San) Plant No. 1 activated sludge facility (AS1) contains 26 rectangular clarifiers that use chain and flight mechanisms to collect sludge that settles along the length of the clarifiers. Over time, the collectors are subject to degradation and wear. Clarifiers 11 and 13 sludge collectors have reached the end of their useful life and have been out of service since December 2023.

RELEVANT STANDARDS

* Sustain 1, 5, and 20-year planning horizons
* Maintain a proactive asset management program
* 24/7/365 treatment plant reliability

PROBLEM

The collectors in Clarifiers 11 and 13 at AS1 are inoperative and at the end of their useful life and need to be overhauled to provide a reliable and redundant sludge clarification system.

PROPOSED SOLUTION

Approve a Services Contract for Activated Sludge Clarifiers 11 and 13 Rehabilitation at Plant No. 1 (MP1-017), Specification No. S-2025-692BD, to restore the chain and flight systems.

TIMING CONCERNS

Delays in approving this rehabilitation (overhaul) may result in limited secondary treatment capacity and redundancy to treat peak wet weather flows.

RAMIFICATIONS OF NOT TAKING ACTION

Not rehabilitating the two clarifiers will increase the risk of not being able to adequately treat the AS1 flows.

PRIOR COMMITTEE/BOARD ACTIONS

N/A

ADDITIO...