File #: 2024-3954    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 11/7/2024 In control: OPERATIONS COMMITTEE
On agenda: 11/20/2024 Final action: 11/20/2024
Title: SOUTH PERIMETER WALL AND SOIL IMPROVEMENTS AT PLANT NO. 2, CONTRACT NO. P2-128A AS PART OF DIGESTER REPLACEMENT AT PLANT NO. 2, PROJECT NO. P2-128
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. P2-128A Professional Construction Services Agreement
Related files: 2023-2988
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
SOUTH PERIMETER WALL AND SOIL IMPROVEMENTS AT PLANT NO. 2, CONTRACT NO. P2-128A AS PART OF DIGESTER REPLACEMENT AT PLANT NO. 2, PROJECT NO. P2-128
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Approve a Professional Construction Services Agreement with Brown and Caldwell to provide construction support services for South Perimeter Wall and Soil Improvements at Plant No. 2, Contract No. P2-128A for a total amount not to exceed $2,043,717; and

B. Approve a contingency of $204,371 (10%).
body

BACKGROUND

Brown and Caldwell was selected as part of a competitive, qualifications-based solicitation process to design the South Perimeter Wall and Soil Improvements project at Plant No. 2, Contract No. P2-128A. At the time of the solicitation, the Orange County Sanitation District (OC San) documented its intent to award a subsequent agreement to the design consultant for continuation of engineering services during construction.

This project will replace the perimeter chain link fence at Plant No. 2 along the Talbert Marsh with a cast-in-place concrete wall to protect the facilities from lateral spread, sea level rise, and meet OC San's security requirements.

RELEVANT STANDARDS

* Comply with California Government Code Section 4526 to engage the best qualified firm "on the basis of demonstrated competence and qualifications" and "negotiate fair and reasonable fees"
* Ensure public's money is wisely spent

PROBLEM

This project requires the design consultant to provide as-needed services during construction including submittal review, responding to the Contractor's requests for information, reviewing construction change orders, participating in meetings, attending site visits, and preparing record drawings. Given the project's location and the extensive excavation and soil stabilization involved, the design consulta...

Click here for full text