FROM:                     James D. Herberg, General Manager

                     

SUBJECT:

 

title

GENERAL MANAGER’S FY 2021-2022 WORK PLAN MID-YEAR UPDATE

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  Recommend to the Board of Directors to:

Receive and file the General Manager’s FY 2021-2022 Work Plan Mid-Year Update.

body

 

BACKGROUND

 

Each year, the General Manager prepares a work plan of activities supporting Orange County Sanitation District’s (OC San) strategic goals and initiatives to be accomplished during the fiscal year.  The General Manager’s FY 2021-2022 work plan was approved by the Steering Committee and Board of Directors in August 2021.  Attached is the mid-year update for the General Manager’s FY 2021-2022 Work Plan.

 

RELEVANT STANDARDS

 

                     Maintain a culture of improving efficiency to reduce the cost to provide the current service level or standard

                     Cultivate a highly qualified, well-trained, and diverse workforce

                     Maintain and adhere to appropriate internal planning documents (Biosolids, Odor, and Energy Master Plans)

                     Use all practical and effective means for resource recovery

 

PRIOR COMMITTEE/BOARD ACTIONS

 

July 2021 - Steering Committee received and filed the FY 2021- 2022 General Manager’s Proposed Work Plan.

 

August 2021 - Steering Committee and Board of Directors approved the General Manager’s FY 2021-2022 Work Plan.

 

ADDITIONAL INFORMATION

 

The General Manager’s work plan includes 23 goals for the fiscal year.  Five items in the work plan have been completed.

 

FINANCIAL CONSIDERATIONS

 

All items included in the General Manager’s Work Plan were budgeted in the FY 2021-2022 Budget.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     General Manager’s FY 2021-2022 Work Plan Mid-Year Update