Legislation Details

File #: 2026-4922    Version: 1 Name:
Type: Consent Status: Final
File created: 5/13/2026 In control: OPERATIONS COMMITTEE
On agenda: 6/3/2026 Final action:
Title: HEADWORKS STANDBY GENERATOR NO. 1 AND EPSA STANDBY GENERATOR NO. 3 RADIATOR REPLACEMENTS AT PLANT NO. 2 (MP2-029), SPECIFICATION NO. S-2026-722BD
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report, 2. General Services Contract, S-2026-722BD
FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance

SUBJECT:

title
HEADWORKS STANDBY GENERATOR NO. 1 AND EPSA STANDBY GENERATOR NO. 3 RADIATOR REPLACEMENTS AT PLANT NO. 2 (MP2-029), SPECIFICATION NO. S-2026-722BD
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

A. Approve a General Services Contract to Minako America Corporation DBA Minco Construction, for Headworks Standby Generator No. 1 and EPSA Standby Generator No. 3 Radiator Replacements at Plant No. 2 (MP2-029), Specification No. S-2026-722BD, for a total amount not to exceed $474,000; and

B. Approve a contingency of $47,400 (10%).
body

BACKGROUND

The Effluent Pump Station Annex (EPSA) generators provide emergency back-up power for the EPSA pumps and the Ocean Outfall Booster Station (OOBS) pumps. The headworks generators are used to generate back-up power for the main sewage pumps, the washer compactors, the odor control system and ancillary equipment.

RELEVANT STANDARDS

* Protect OC San assets
* 24/7/365 treatment plant reliability
* Maintain a proactive asset management program

PROBLEM

During routine preventative maintenance, Orange County Sanitation District (OC San) discovered coolant leaking from Headworks Generator No. 1 and EPSA Generator No. 3. Further inspection determined that both radiators were leaking coolant. Although multiple repairs were made, the leaks persisted.



PROPOSED SOLUTION

Approve a General Services Contract to replace both radiators for Headworks Standby Generator No. 1 and EPSA Standby Generator No. 3 with in-kind equipment to restore the full operational capacity and reliability of the standby generation systems.

TIMING CONCERNS

Due to the long lead times for replacement parts and the critical nature of these generators, it is essential to begin this work as soon as possible to maintain operational readiness.

RAMIFICATIONS ...