Legislation Details

File #: 2026-5199    Version: 1 Name:
Type: Consent Status: Final
File created: 11/12/2026 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2026 Final action:
Title: PLANT NO. 2 SPARE PLANT WATER PUMP
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report
FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance

SUBJECT:

title
PLANT NO. 2 SPARE PLANT WATER PUMP
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Approve a Sole Source Purchase Order to G3 Engineering, Inc. for the purchase of one Floway Pump for Plant No. 2 Spare Plant Water Pump for a total amount not to exceed $209,958 plus applicable sales tax and freight charges; and

B. Approve a contingency of $20,996 (10%).
body

BACKGROUND

The Plant Water Pump Station at Orange County Sanitation District (OC San) Plant No. 2 operates four Floway vertical turbine pumps installed under Project No. J-117B. The station distributes treated water throughout the plant, including cooling water for the Central Generation (CenGen) system, supporting critical plant processes and maintenance activities.

RELEVANT STANDARDS

24/7/365 treatment plant reliability
Protect OC San assets
Maintain a proactive asset management program

PROBLEM

OC San does not currently have a spare plant water pump. Failure of an existing pump could result in extended downtime due to the 26-week replacement lead time, potentially impacting CenGen cooling and other critical plant operations.

PROPOSED SOLUTION

Purchase one spare Floway Pump for plant water through G3 Engineering, Inc., the identified authorized distributor, to maintain equipment reliability and minimize downtime following a pump failure.

TIMING CONCERNS

The replacement pump has an estimated 26-week delivery lead time. Delaying procurement increases the risk of prolonged equipment downtime if an existing pump fails.

RAMIFICATIONS OF NOT TAKING ACTION

Without an available spare, a pump failure could result in prolonged equipment downtime, reduced plant water system reliability, and potential interruptions to CenGen cooling and other critical plant processes.

PRIOR COMMITTEE/BOARD ACTIONS

N/A

ADDITIONAL INFORMATION

G3 En...