FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance
SUBJECT:
title
PLANT NO. 2 SPARE BAR SCREEN CARRIAGE ASSEMBLY
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION: Recommend to the Board of Directors to:
A. Approve a Sole Source Purchase Order to Veolia WTS Services USA Inc., for the purchase of one spare bar screen carriage assembly for a total amount not to exceed $268,168 plus applicable sales tax & freight charges; and
B. Approve a contingency of $26,817 (10%).
body
BACKGROUND
Orange County Sanitation District (OC San) Plant No. 2 utilizes mechanical bar screens at the Headworks Facility to remove debris and large solids from incoming wastewater, protecting downstream treatment equipment and maintaining reliable plant operations. The bar screen carriage assemblies use mechanical rakes to remove accumulated debris and maintain wastewater flow.
Plant No. 2 also operates in a split-mode configuration, utilizing three designated bar screens to process wastewater for the Groundwater Replenishment System (GWRS). Maintaining sufficient bar screen availability is essential to supporting split-mode operations and meeting GWRS water quality requirements.
RELEVANT STANDARDS
24/7/365 treatment plant reliability
Protect OC San assets
Protect public safety
Maintain a proactive asset management program
PROBLEM
OC San does not currently have a spare bar screen carriage assembly. A failure requiring replacement could result in extended equipment downtime due to the 18-week fabrication lead time, potentially disrupting split-mode operations and reducing treatment flexibility.
PROPOSED SOLUTION
Procure one spare bar screen carriage assembly from the Original Equipment Manufacturer (OEM), Veolia WTS Services USA, Inc., to minimize equipment downtime and maintain operational reliability.
TIMING CONCERNS
The replacement carriage assembly requires approximately 18 weeks fo...