File #: 2022-2619    Version: 1 Name:
Type: Consent Status: Passed
File created: 11/2/2022 In control: OPERATIONS COMMITTEE
On agenda: 6/7/2023 Final action: 6/7/2023
Title: INFLUENT PUMP STATION PLANT WATER PIPING REPAIR AT PLANT NO. 2, PROJECT NO. FR2-0029
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. FR2-0029 Contract Agreement
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
INFLUENT PUMP STATION PLANT WATER PIPING REPAIR AT PLANT NO. 2, PROJECT NO. FR2-0029
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Receive and file Bid Tabulation and Recommendation for Influent Pump Station Plant Water Piping Repair at Plant No. 2, Project No. FR2-0029;

B. Award a Construction Contract to W.A. Rasic Construction Company, Inc. for Influent Pump Station Plant Water Piping Repair at Plant No. 2, Project No. FR2-0029, for a total amount not to exceed $177,063; and

C. Approve a contingency of $35,400 (20%).
body

BACKGROUND

The Orange County Sanitation District's (OC San) Headworks Bar Screen Facility provides vital preliminary treatment to all incoming wastewater by removing trash and debris that would otherwise damage downstream treatment equipment. Water is supplied from the adjacent Influent Pump Station and used in the sluiceways to remove and transport the debris from the bar screens for disposal. Plant No. 2 Headworks was constructed in 2012 under Project No. P2-66, Headworks at Plant No. 2.

RELEVANT STANDARDS

* Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder
* 24/7/365 treatment plant reliability

PROBLEM

An 8-inch pipeline supplies water to the Influent Pump Station, which then supplies water to the bar screen sluiceways through two 6-inch pipelines. The 8-inch and one of the 6-inch pipelines have failed. The facility is currently relying on a temporary supply line and a 6-inch pipeline.

PROPOSED SOLUTION

Award a construction contract for Influent Pump Station Plant Water Piping Repair at Plant No. 2, Project No. FR2-0029. This project will replace existing, failed underground sections of pipe to provide reliable sluice water to the Bar Screen Facility.